4.3 Putting into Service

After tests have been performed satisfactorily the Argus should be put back into service as follows:-
Remove all test connections.
Where possible the Argus settings should be down loaded to a computer and a printout of the settings produced.
This should then be compared against the required settings. It is important that the correct settings group is active
if more than one group has been programmed.
Reset all event, waveform and fault records and reset all counters.
Replace all secondary circuit fuses and links, or close m.c.b's.