Grounding Considerations:
Has proper, 10AWG braided, ground wire been provided to the 12"x12" box?
Network Considerations:
Are STATIC IP addresses assigned and confirmed? (static IP, subnet mask, default gateway)
What is the hospitals network bandwidth?
If video conferencing is installed, what is the hospitals external IP and are the correct ports open?
IP
Are all required Network drops in place?
Equipment Mounting Considerations:
Is proper backing material installed for wall mounted equipment? (monitors, equipment rack, wall camera)
Yes or no.
Are the Booms installed?
Non-Skytron Equipment Considerations:
Is there any special or custom equipment the installer(s) may not be familiar with?
Are all customer provided systems and equipment in place and in working order?
Are non Skytron supplied displays on site?
Have proper power supplies been provided for non Skytron displays?
Are proper mounts or adapters provided for monitors?
** R
ETURN VISITS DUE TO INACCURATE
Skytron Representative :
Signature:
Hospital Representative:
Signature:
Contractor Representative:
Signature:
Other Representative (A):
Signature:
Other Representative (B):
Signature:
SkyVision Linx 300 Pre-Install• REV2
ports open?
Yes or no.
Type
Yes or no.
Yes or no.
/
INCOMPLETE INSTALLATION VERIFICATION ARE SUBJECT TO BILLING
Printed Name:
____________________________________________________
____________________________________________________
____________________________________________________
____________________________________________________
____________________________________________________
Yes or no.
Yes or no.
Yes or no.
Yes or no.
Yes or no.
Yes or no.
Date:
Page 21
FDA 0900-36 REV0
Yes or no.
**
Page 2 of 3

Hide quick links:

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the Linx 300 and is the answer not in the manual?

Questions and answers

Table of Contents