B&D Roll-A-Door R1D Installation Instructions Manual
B&D Roll-A-Door R1D Installation Instructions Manual

B&D Roll-A-Door R1D Installation Instructions Manual

B&d roll-a-door series roller garage doors
Hide thumbs Also See for Roll-A-Door R1D:

Advertisement

Roll-A-Door
®
Series 1 includes R1D, R1F, R1R, R1M, R1ME
WINDRATED INSTALLATION INSTRUCTIONS
DISCLAIMER
THESE INSTRUCTIONS ARE INTENDED FOR
PROFESSIONAL GARAGE DOOR INSTALLERS
Note: All references are taken from inside looking out
Part No. 52214. Revision 2 December 2013

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the Roll-A-Door R1D and is the answer not in the manual?

Questions and answers

Summary of Contents for B&D Roll-A-Door R1D

  • Page 1 Roll-A-Door ® Series 1 includes R1D, R1F, R1R, R1M, R1ME WINDRATED INSTALLATION INSTRUCTIONS DISCLAIMER THESE INSTRUCTIONS ARE INTENDED FOR PROFESSIONAL GARAGE DOOR INSTALLERS Note: All references are taken from inside looking out Part No. 52214. Revision 2 December 2013...
  • Page 2: Table Of Contents

    Series 1 Windrated Installation Instructions CONTENTS BEFORE YOU START SAFETY CHECKLIST FASTENER RECOMMENDATIONS FOR FITTING GARAGE DOORS REQUIREMENTS BEFORE INSTALLATION FIXING REQUIREMENTS TOOLS CHECKLIST PARTS CHECKLIST INSTALLATION INSTALL FIRST BRACKET INSTALL SECOND BRACKET PLACE DOOR ON BRACKETS POSITION DOOR TENSION THE SPRINGS NOTCHING BOTTOM RAIL ATTACHING STOP S02H...
  • Page 3: Before You Start

    Series 1 Windrated Installation Instructions 1.0 BEFORE YOU START Your new B&D Roll-A-Door ® has been designed to provide security, attractive appearance and smooth, low effort operation. Your door will not provide optimum performance unless it is installed correctly. For satisfactory door operation please follow the instructions carefully.
  • Page 4: Fastener Recommendations For Fitting Garage Doors

    Series 1 Windrated Installation Instructions 1.2 FASTENER RECOMMENDATIONS FOR FITTING GARAGE DOORS DIAMETER LENGTH OF FASTENER MATERIAL FASTENER TYPE(S) OR TYPE (See Note) 100mm New Solid Brick Anchor Screws or Equivalent 3/8” 60mm 100mm New Solid Concrete Anchor Screws or Equivalent 3/8”...
  • Page 5: Requirements Before Installation

    Series 1 Windrated Installation Instructions 1.3 REQUIREMENTS BEFORE INSTALLATION OPENING REQUIREMENTS The door is designed to be mounted behind the opening, therefore you will need to measure and check: HEAD ROO M 350mm OPENING WIDTH - As the door overlaps each side by 55mm or more, the door should be 110mm wider than the 460mm opening.
  • Page 6: Fixing Requirements

    Series 1 Windrated Installation Instructions 1.4 FIXING REQUIREMENTS The installer must select and use fasteners appropriate to the material into which they are being fixed. Refer to fastener recommendations on page 4 and drawings S01E, S02E, S03E. NOTE: It is the installer’s responsibility to ensure that the fixing methods are sound. 1.5 TOOLS CHECKLIST Tools required to install the door.
  • Page 7: Installation

    Series 1 Windrated Installation Instructions 2.0 INSTALLATION 2.1 INSTALL FIRST BRACKET a) Measure the door curtain width and mark where edge of the curtain will be, allowing for over lap on each side of the opening. 230mm Restricted or b) Add clearance of 35 to 75mm from edge of curtain to inside edge 250mm Normal Headroom of bracket to determine positioning of the bracket.
  • Page 8: Place Door On Brackets

    Series 1 Windrated Installation Instructions EQUAL EQUAL 2.3 PLACE DOOR ON BRACKETS a) Check the axle length and cut if sideroom is limited. Before cutting, make sure the floating axle is free and centred. Centre will be found by rotating the axle a quarter turn in either direction then releasing . With centre found, make a clear mark on the axle against the hub for later reference.
  • Page 9: Tension The Springs

    Series 1 Windrated Installation Instructions 2.5 TENSION THE SPRINGS FIRST PREPARE A SOFT WOOD CHOCK, ABOUT 400mm LONG. WOOD CHOCK THEN - Ensure that bottom rail is at the 3 o’clock position as shown WOOD CHOCK in Step 2.4. a) Ensure both “U” bolts are tightened, then - 1.
  • Page 10: S02H

    Series 1 Windrated Installation Instructions 2.8 S02H Revision 2 December 2013...
  • Page 11: S03H

    Series 1 Windrated Installation Instructions 2.9 S03H Revision 2 December 2013...
  • Page 12: S04H

    Series 1 Windrated Installation Instructions 2.10 S04H Revision 2 December 2013...
  • Page 13: Guides

    Series 1 Windrated Installation Instructions 2.11 GUIDES a) Check that curtain overlaps equally on both sides. RESTRICTED HEADROOM 35mm b) Check that guides are the correct length, that is, level with the brackets (or in the restricted headroom position are 35mm maximum above bracket).
  • Page 14: Centre Lift Lock

    Series 1 Windrated Installation Instructions 2.13 CENTRE LIFT LOCK a) Raise the curtain until the lock corrugation is visible above the door guides. b) Install locking bar retainer in line with lock corrugation by pushing retainer towards door edge, sliding the legs under the Nylofelt ®...
  • Page 15: Final Adjustment

    Series 1 Windrated Installation Instructions 2.14 FINAL ADJUSTMENT 1. If the door is hard to operate in ANY DIRECTION check that the door is not jamming in the guides. Check: a) the guide clearances; b) that guides are plumb; c) that the guide surfaces are clean and free from oil; d) that locking bars are the correct length;...
  • Page 16: Fixing Alternatives

    Series 1 Windrated Installation Instructions 2.16 FIXING ALTERNATIVES 1. ALTERNATIVE BRACKET FITTING An “A2”extended leg bracket should be used in conjunction with the standard “A” style bracket. SEC URE IF PO SSIBLE “A” BRAC KET SEC URE W ITH MASO NRY ANC HO RS “A2”...
  • Page 17: After Installation Care

    Series 1 Windrated Installation Instructions 3.0 AFTER INSTALLATION CARE GENERAL CARE OF YOUR ROLL-A-DOOR ® REGULAR MAINTENANCE REQUIRED B&D recommends that you check the operation of your Roll-A-Door ® CLEANING at least every six months (more regularly in extreme environments or frequent use).