3.5

VENTILATION AND COOLING

Fig. 3.5-1 Installation on plain floor
The heat produced by the UPS is transferred to the environment by its ventilation.
Air inlets for UPS ventilation are located on the front of the UPS, while air outlets are on top
of the cabinet.
A suitable ventilation or cooling system must be installed to extract the heat from the UPS
room.
Air filtration systems could be required when the UPS operates in a dirty environment.
Contact your Dealer or the nearest Service Center for appropriate solutions.
In order to prevent overheating of the UPS, the available air intake flow rate must exceed the
total air exhaust flow rate requirement of the UPS system.
The below table indicates the heat dissipation at full Load at PF = 0.8 lag. and charged
Battery, up to 3,280 ft (1,000 m) altitude, for cooling air 77°F (25°C) to 86°F (30°C).
UPS rating
SG Series 225 kVA
SG Series 300 kVA
OPM_SGS_ISG_M22_M30_0US_V011.doc
Do not put anything on the top of the cabinet.
Losses
BTU / hr
kW
50,512
14.80
64,164
18.80
15/38
Fig. 3.5-2 Installation on raised floor
Cooling air flow
CFM
2,541
3,228
Installation Guide SG Series 225 & 300 kVA
GE
3
m
/ h
4,317
5,484