Page 1
Power Optimizer For Europe P650 / P701 / P730 / P800p / P801 / P850 / P950 / P1100 YEAR WARRANTY PV power optimization at the module level The most cost-effective solution for commercial and large field installations Specifically designed to work with SolarEdge...
Page 2
OUTPUT DURING OPERATION ( POWER OPTIMIZER CONNECTED TO OPERATING SOLAREDGE INVERTER ) Maximum Output Current Maximum Output Voltage OUTPUT DURING STANDBY ( POWER OPTIMIZERDISCONNECTED FROM SOLAREDGE INVERTER OR SOLAREDGE INVERTER OFF ) 1 ± 0.1 Safety Output Voltage per Power Optimizer...
Page 3
OUTPUT DURING OPERATION ( POWER OPTIMIZER CONNECTED TO OPERATING SOLAREDGE INVERTER ) Maximum Output Current Maximum Output Voltage OUTPUT DURING STANDBY ( POWER OPTIMIZER DISCONNECTED FROM SOLAREDGE INVERTER OR SOLAREDGE INVERTER OFF ) Safety Output Voltage per Power Optimizer 1 ± 0.1...
Page 4
SolarEdge is a global leader in smart energy technology. By leveraging world-class engineering capabilities and with a relentless focus on innovation, SolarEdge creates smart energy solutions that power our lives and drive future progress. SolarEdge developed an intelligent inverter solution that changed the way power is harvested and managed in photovoltaic (PV) systems.
Page 6
The material furnished in this document is believed to be accurate and reliable. However, SolarEdge assumes no responsibility for the use of this material. SolarEdge reserves the right to make changes to the material at any time and without notice. You may refer to the SolarEdge web site (www.solaredge.com) for the most updated version.
Page 7
Model and serial number of the product in question The error indicated on the inverter screen or on the SolarEdge monitoring portal, if there is such an indication. System configuration information, including the type and number of modules connected and the number and length of strings.
Page 8
Step 3, Connecting Power Optimizers in Strings..............14 Step 4, Providing Installation Information ................15 Step 5, Verifying Proper Power Optimizer Connection............15 Step 6, Disabling SafeDC™ (Only when Connecting to Non-SolarEdge Inverters without SMI) 16 Step 7, Commissioning ......................17 Appendix A: Troubleshooting ................... 18 For Installations with SolarEdge Inverters ...............18...
Page 9
Cette unité doit être opérée suivant les instructions trouvées dans ce document. CAUTION: Cutting the power optimizer input or output cable connector is prohibited and will void the warranty. Sectionner les cables d’entrées ou de sortie de l’optimiseur est interdit et annule sa garantie. SolarEdge Power Optimizers Installation Guide – MAN-01-00112-1.2...
Page 10
In order to ensure mechanical compatibility of the SolarEdge optimizers and the modules to which they are connected: Use identical connectors from the same manufacturer and of the same type on both the ...
Page 11
Each power optimizer is equiped with a SafeDC mechanism which ensures the optimizer outputs a safe 1V voltage until connected to the SolarEdge inverter or SMI, and the inverter/SMI are turned When connecting the power optimizers to a non-SolarEdge inverter without a Safety and monitoring Interface, you must disable the SafeDC before connecting to the inverter.
Page 12
Each power optimizer transmits its module’s performance data over the DC power line. When using a SolarEdge inverter, these signals are received by the inverter and can be used for maintenance and remote monitoring. To monitor the modules when using a non-SolarEdge inverter, add a SolarEdge Safety and monitoring interface device (purchased separately).
Page 13
Site Installation General Workflow The following is the workflow for installing and setting up a new site, using a SolarEdge inverter or a non- SolarEdge one (with or without SMI). Most of these procedures can also be used for modifying an existing site.
Page 14
Installing the SolarEdge inverter Refer to SolarEdge Inverter Installation Connecting the strings to the Manual inverter Commissioning and activating the installation Connecting the inverter to the SolarEdge monitoring server (optional) Configuring the inverter (optional) SolarEdge Power Optimizers Installation Guide – MAN-01-00112-1.2...
Page 15
Refer to the SolarEdge Site Designer for verification. You can download the software from http://www.solaredge.com/groups/support/downloads Figure 1: Power Optimizers Connected in Series to SolarEdge Inverter...
Page 16
Figure 3: Power optimizers connected in series directly to a non-SolarEdge inverter Installation Equipment List Standard tools can be used during the installation of the SolarEdge power optimizer. The following is a recommendation of the equipment to be used: ...
Page 17
The grounding washer should break through the anodize coating of the railing to ensure low-resistive connection. Apply torque of 9.5 N*m / 7 lb*ft. Star washer Mounting Bracket Figure 4: Power optimizer grounding using the star washer SolarEdge Power Optimizers Installation Guide – MAN-01-00112-1.2...
Page 18
NOTE: Record power optimizer serial numbers and locations, as described in Step 4, Providing Installation Information on page 15. Verify that each power optimizer is securely attached. For additional information, refer to http://www.solaredge.com/files/pdfs/se-product-update-dcd-c-grounding-lug.pdf. SolarEdge Power Optimizers Installation Guide – MAN-01-00112-1.2...
Page 19
Connect the rest of the power optimizers in the string in the same way. While the modules are exposed to sunlight, verify correct polarity by measuring the string polarity with a voltmeter. Figure 7: Power optimizers connected in series SolarEdge Power Optimizers Installation Guide – MAN-01-00112-1.2...
Page 20
Fill out the Physical Layout Template using the detachable 2D barcode stickers on each power optimizer. Once the form is completed, scan it and upload the scanned file to the SolarEdge monitoring portal during site registration. For an example paper template, refer to http://www.solaredge.com/files/pdfs/physical-...
Page 21
SolarEdge power optimizers are provided in a SafeDC mode: when connected to a PV module these power optimizers will output a safe voltage of 1VDC until they are paired either with a SolarEdge inverter or with the SolarEdge Safety & Monitoring Interface, and until power production has started.
Page 22
Connect the strings to the inverter: When connecting to SolarEdge inverters, or to non-SolarEdge inverters with SMI, perform the Commissioning steps as described in the SolarEdge Inverter Installation Manual, or SolarEdge SMI Installation Manual, available on the SolarEdge website at http://www.solaredge.com/groups/support/downloads.
Page 23
Do not continue before finding the problem and replacing the malfunctioning power optimizer. SafeDC mode was disabled Enable the SafeDC. using the SolarEdge Key SolarEdge Power Optimizers Installation Guide – MAN-01-00112-1.2...
Page 24
For installation with safety & not connected properly to their monitoring interface: power optimizer inputs Turn OFF the SMI Wait ~30sec until all optimizers are in SafeDC mode Measure the string output using a voltmeter SolarEdge Power Optimizers Installation Guide – MAN-01-00112-1.2...
Page 25
The inverter is not The inverter voltage is below Refer to inverter manual or module waking up wakeup voltage datasheet to determine the minimum string length SolarEdge Power Optimizers Installation Guide – MAN-01-00112-1.2...