Download Print this page

BITMAIN ANTSPACE HK3 V2 Installation Manual

Liquid cooling system
Hide thumbs Also See for ANTSPACE HK3 V2:

Advertisement

Quick Links

AntSpace HK3 Liquid Cooling System On-Site Installation Manual V1.2
ANTSPACE HK3
V2/V3/V5
Liquid Cooling System
On-Site Installation Manual

Advertisement

loading
Need help?

Need help?

Do you have a question about the ANTSPACE HK3 V2 and is the answer not in the manual?

Questions and answers

Summary of Contents for BITMAIN ANTSPACE HK3 V2

  • Page 1 AntSpace HK3 Liquid Cooling System On-Site Installation Manual V1.2 ANTSPACE HK3 V2/V3/V5 Liquid Cooling System On-Site Installation Manual...
  • Page 2 Catalogue ANTSPACE HK3 Product components ANTSPACE HK3 Installation between the container and the cooling tower ANTSPACE HK3 Installation of the exhaust fan of the container ANTSPACE HK3 The layout and installation of the intermediate connecting pipelines ANTSPACE HK3 Power distribution management ANTSPACE HK3 Pressure operation ANTSPACE HK3 Liquid filling operation ANTSPACE HK3 Site installation summary...
  • Page 3 AntSpace HK3 Liquid Cooling System On-Site Installation Manual 一、 ANTSPACE HK3 Product components ANTSPACE liquid cooling system is mainly composed of a container, a cooling tower, intermediate connecting pipelines and other related accessories, its functions as shown in Table 1-1. Cooling tower Container WBGL04...
  • Page 4 AntSpace HK3 Liquid Cooling System On-Site Installation Manual Cooling tower Container 2000 mm Figure 2-1 The relative position of the container and the cooling tower 三、 ANTSPACE HK3 Installation of the exhaust fan of the container After the relative position of the container and the cooling tower is determined, find the exhaust fan in the water tank of the container, unpack it and install it.
  • Page 5 AntSpace HK3 Liquid Cooling System On-Site Installation Manual 四、 ANTSPACE HK3 The layout and installation of the intermediate connecting pipelines Flange junction Chuck connection Outlet pipe of the cooling tower Inlet pipe of the cooling tower Figure 4-1 Installation of the intermediate connecting pipelines Pipeline connection: First of all, find two supply and return pipes (short, universal, with valves on the pipe) in the container wooden box, labeled GL14 and GL15;...
  • Page 6 AntSpace HK3 Liquid Cooling System On-Site Installation Manual Figure 4-3 The direction of the handle of the butterfly valve Next, find out the wooden boxes with the numbers "WBGL01", "WBGL02", " 008.WBGL03", "WBGL04", "WBGL05", "WBGL06" and "WBGL07"; then find the flanges, chuck washers and connecting bolts and clamps from the wooden box.
  • Page 7 AntSpace HK3 Liquid Cooling System On-Site Installation Manual Cable inlet hole Cable inlet hole Figure 5-1 Cable inlet hole Both sides of the container have grounding studs, and PDC must also be grounded securely. Therefore, ensure that both the container shell and PDC shell are grounded securely. When leaving the factory, the phase sequence of the equipment has been determined.
  • Page 8 AntSpace HK3 Liquid Cooling System On-Site Installation Manual / 2 nut and gasket from the cooling tower spare parts box, remove the cooling tower air inlet grid, install the liquid level sensor from inside to outside, and install the liquid level sensor as shown in figure 5-4 below. The indicator point (depression) - upwards required...
  • Page 9 AntSpace HK3 Liquid Cooling System On-Site Installation Manual Figure 5-4 Installation diagram of liquid level sensor 六、 ANTSPACE HK3 Pressure operation Preparation for the pressure test: 1) Get hoses and air pumps ready; (Recommended brand: Outstanding, model 2200W-40L; Selection basis: The internal volume of the system is about 1.5m /h, and the corresponding exhaust volume air pump is selected according to the time requirements;...
  • Page 10 AntSpace HK3 Liquid Cooling System On-Site Installation Manual NO.2 Air Vent Valve NO.1 Air Vent Valve Automatic breathing valve Figure 5-1 Pump station - automatic exhaust valve Status of closing: The vent of the automatic Status of opening: The vent of the exhaust valve is blocked with a plug.
  • Page 11 AntSpace HK3 Liquid Cooling System On-Site Installation Manual Automatic exhaust valve Figure 5-3 External connecting pipelines - automatic exhaust valve Status of closing: the handle of ball valve is perpendicular to the pipeline. Status of opening: the handle of ball valve is parallel to the pipeline.
  • Page 12 AntSpace HK3 Liquid Cooling System On-Site Installation Manual 4) Connect the air pipe to any fast plug-in interface, and close the corresponding ball valve. Port of air pump Mini ball valve Bellows Close this ball valve Figure 5-5 System - ball valve for connecting pipelines 5)...
  • Page 13 AntSpace HK3 Liquid Cooling System On-Site Installation Manual Computing equipment Chuck connection Figure 5-6 System - chuck connection Flange joint Welded joint Thread joint Figure 5-7 System - Flange/thread/welded joints 7) The check methods are as follows: a) Seeing, hearing and touching are applicable to leakage inspection. b)...
  • Page 14 AntSpace HK3 Liquid Cooling System On-Site Installation Manual suspected leakage points, especially at the connections. The part with bubbles is the leak point. 七、 ANTSPACE HK3 Liquid filling operation System rehydration consists of four steps: 1) Preparation: prepare materials and tools and open all exhaust valves of the system; 2)...
  • Page 15 AntSpace HK3 Liquid Cooling System On-Site Installation Manual NO.2 Air Vent Valve NO.1 Air Vent Valve Automatic breathing valve Figure 7-1 Internal container - automatic exhaust valve NO.4 Air Vent NO.6 Air Vent Valve Valve NO.5 Air Vent Valve NO.3 Air Vent Valve Figure 7-2 Internal container - plug - 13 -...
  • Page 16 AntSpace HK3 Liquid Cooling System On-Site Installation Manual Automatic exhaust valve Figure 7-3 External connecting pipelines - automatic exhaust valve Step 2-3:Procedures for the coolant charge: 1) A self-priming pump must be installed outside the container,The self-priming pump needs to inject liquid into the pump head for the first time.
  • Page 17 AntSpace HK3 Liquid Cooling System On-Site Installation Manual Filling pump NO.9 Ball Valve NO.2 Pressure Gauge NO.8 Ball Valve Safety valve NO.6 Ball Valve NO.7 Ball Valve Figure 7-5 Pump station - charging valve Manual liquid filling port Liquid level meter Figure 7-6 Pump station - liquid level meter 2)...
  • Page 18 AntSpace HK3 Liquid Cooling System On-Site Installation Manual Figure 7-7 pressure sensor reading on main interface 6) Then open the circulation pump again, circulate the medium in the system, ensure that the exhaust valves are all opened. 7) Then open NO.6 Ball Valve, close NO.7 Ball Valve, click on the refilling pump on the touch screen interface, and turn it on.
  • Page 19 AntSpace HK3 Liquid Cooling System On-Site Installation Manual Operation of cooling system Gas check 7bar / 12h and liquid check 7bar / 30min Preparatory work - system rehydration - water tank Filling operation of cooling system rehydration - periodic rehydration After the equipment arrives at the site, it needs to be installed according to the sequence in table 8-1.

This manual is also suitable for:

Antspace hk3 v3Antspace hk3 v5