3) Crimp the insulation part
• Position the cable on the insulation crimping part and crimp it with a
hand crimping tool.
• Crimp at position Ⓓ (50~60A) (Based on the IWS-5100A crimper)
• Crimp it by pressing firmly in the same way as with the conductor part.
completed crimping appearance
4) Connector assembly
Repeat 1) to 3) for the each cables(+ and -).
Assemble the completed crimped cables into the connector housing.
CAUTION
* The connector housing has labels attached on the left and right sides, so please
assemble the terminals in the correct position.
3 Commissioning
3.1 LED indicators
The indicators on the top of a battery enclosure show each state.
Green
Red
Remark
All LED is Off
Green, Red blink
simultaneously
(On : 1s, Off : 1s)
Green blinks
(On : 1s, Off : 1s)
Green is On
Green blinks
(On : 1s, Off : 4s)
Red blinks
(On : 3s, Off : 3s)
Red is On
Green, Red blink alternately
(On : 1s, Off : 1s)
Red blinks for 1 minute
(On : 1s, Off : 1s)
Note
This is the standard LED indicators of the enblock E, and please note that the state
may be different depending on the matching inverter.
Green Red
State
OFF state
INIT state (initial start-up)
STANDBY state
(ready to operate)
Operation state
(including pre-charging)
Power Saving state
Fault 1
Fault 2
SW update state
SW update fail