TJ1600 Product Family Installation and Commissioning Guide v5.0
Note: The requirements for Installation clearance and spacing between systems for
solid-wall cabinets are not in the scope of this document.
Following figure shows the recommended spacing (minimum) and airflow for stacked
systems:

Figure 1: Spacing and airflow recommendation for stacked systems

2.2.4 Guidelines for populating pluggable in chassis

Follow the guidelines mentioned when populating pluggable in the chassis. Do the
following recommendations for an improved thermal performance:
Always cover an empty slot with an appropriate filler panel to prevent overheating
and entry of dust into the chassis.
Protect the pluggable modules or unused ports by inserting clean dust caps to
prevent the entry of dust and for optical safety.
Follow the recommended order for populating pluggable in the chassis.
Recommended order of pluggable installation
The sequence for installing pluggable (Optical and electrical) depends on the
arrangement of ports in a card. The recommended sequence to install pluggable is
explained in the following with three examples.
Case 1: If a card consists of four ports, all in one row, then install the pluggable starting
from left to right, in an alternate port sequence: port P1 > P3 > P2 > P4.
8
©Tejas Networks Ltd.

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the TJ1600 Series and is the answer not in the manual?

Questions and answers

Subscribe to Our Youtube Channel

This manual is also suitable for:

Tj1600-11Tj1600-6Tj1600-2

Table of Contents

Save PDF