Safety precautions ........................... 7 Technical data of the IC 022 ........................9 Process description ..........................10 Connections and components of the IC 022 ..................11 Connections and components of the front side ................11 Connections and components of the back side ................12 Operation of the blasting gun IG 022 ....................
Violation of requirements for compressed air (see Page • ICS ice cleaning systems s.r.o. retains the copyright on the operator`s manual. These operating instructions are intended for operators and supervision personnel. It contains regulations, drawings and instructions which shall be neither completely used nor disclosed to third parties without express written consent.
Page 8
The workspace has to be closed where necessary, not to endanger third parties. The IC 022 may only be operated by qualified personal and after a thorough training. The user must operate the IC 022 only in flawless condition and repair any damages immediately (see page 18).
Technical data of the IC 022 Length 532 mm Width 287 mm Height 362 mm Weight 19 kg (including hose package) Hopper capacity 4 kg standard Consumption 22 kg/h max. Operation pressure min. 4 bar – max. 10 bar Air consumption 0,3 m³/min- 1,1m³, depending on the chosen...
Process description Before cleaning The dry-ice blasting equipment IC 022 operates with granules of dry-ice pellets Dirty carrying material (Ø3mm), produced through pressing of the CO snow. The pellets Dirt are blasted on the surface to be cleaned. The dirt from the surface is frozen...
Connections and components of the IC 022 Connections and components of the front side Blast gun Hopper lid Emergency stop Pressure gauge Hose package The blasting hose package including the control line is connected firmly with the IC 020. Ver. 1.04.19...
With the pressure control valve you set desired blasting pressure directly on the gun. The IC 022 has a time lag of about 2 seconds to eliminate residual ice from the dosing system and thus avoid icing.
Start-up For the start-up of the IC 022 proceed as follows: 1. Check before each start-up if the pressure control valve is closed. 2. Connect the compressed air hose first with the quick coupling NW 7.2 on the rear of the blasting unit and then with the compressed air source.
For easy transport from one place of work to another within your company, please use the transport handle. For further transport of the IC 022 with a shipping company, we recommend to use the original shipping carton included in the scope of supply.
Pleas note that all works including inspection and maintenance works, especially the works on the safety devices, must be carried out solely by an ICS technician or by a person who can provide proof of receiving a special training on the machines and equipment of ICS ice cleaning system s.r.o.
Maintenance schedule for IC 022 General visual inspection of housing, welding seams, chassis, wheels, screw joints Complete exterior and interior cleaning if required Check the operation of the inlet pressure valve Filter/regulator combination, replace filter, clean and re-adjust Check pneumatic control elements, check for leaks and replace sound absorbers...
Need help?
Do you have a question about the IC 022 and is the answer not in the manual?
Questions and answers