Installation Procedure

1. Note the load tolerance of the floor in the installation location. The SCiB ESS cabinet is 600lbs. (220lbs./ft
2. Take the below clearance requirements for ventilation into account when choosing installation location:
Right Side ........ Zero (0) Inches
Left Side ........... Zero (0) Inches
Top ................... Ten (10) Inches
Front ................. Thirty-Six (36) Inches
Back ................. Zero (0) Inches
3. Refer to the 4400 Installation and Operation Manual for installation steps for the rest of the UPS system.
7.3

Wiring Safety

18
WARNING
Perform wiring and connections with correct polarity.
Be careful when connecting the UPS to the SCiB ESS. A wrong
connection may cause damage to the UPS, ESS, or charger.
DO NOT use excessive force when handling wires.
Do NOT pull or bend wires needlessly.
DO NOT damage wire insulation.
DO NOT place heavy objects on top of the SCiB ESS.
Observe the above precautions when making wire connections or
handling the wires. Failing to observe these precautions may damage
the insulation of the wires or may cause a fire or an electric shock
hazard.
Voltage exists at battery terminals. Proper PPE should be worn
when making electrical connections