2. Secure the switch onto the rack posts.
Mark the location on both posts to ensure it is leveled before securing the switch onto
the rack. (See Figure Below).
For a 4 post rack, first secure the adjustable mounting rail to the back of the switch using the
M4.0*L6.5mm screws provided in the package. Then secure the adjustable mounting rail to the
rack posts. (See Figure Below).
Figure 14.
Figure 15.
S6301-56ST Hardware Installation Guide | 12