NanaWall CSW75 Owner's Manual

Folding center pivot frameless system

Advertisement

Quick Links

Owner' s Manual
NanaWall CSW75
Folding Center Pivot Frameless System
This Owner's Manual contains instructions on the installation, operation, maintenance and warranty of
the NanaWall CSW75 Folding Center Pivot Frameless System. This manual is to be used by the installer
for installation and is to be kept by the Owner for reference. Replacement parts can be ordered directly
through NanaWall Systems.
Nana Wall Systems, Inc.
100 Meadowcreek Drive #250
Corte Madera, CA 94925
800 873 5673
info@nanawall.com
nanawall.com
415 383 3148
Fax 415 383 0312
©2023 Nana Wall Systems, Inc.

Advertisement

loading
Need help?

Need help?

Do you have a question about the CSW75 and is the answer not in the manual?

Questions and answers

Summary of Contents for NanaWall CSW75

  • Page 1 This Owner’s Manual contains instructions on the installation, operation, maintenance and warranty of the NanaWall CSW75 Folding Center Pivot Frameless System. This manual is to be used by the installer for installation and is to be kept by the Owner for reference. Replacement parts can be ordered directly through NanaWall Systems.
  • Page 2 Glass Association of North America (GANA) recommended minimum glass thickness for fully tempered Interior butt glazed fixed glass panels. The installation of the CSW75 system requires a working knowledge and experience in the use of tools, equipment, The CSW75 system is shipped with all necessary and methods necessary for the installation of aluminum components.
  • Page 3 NANAWALL CSW75 OWNER’S MANUAL DIAGRAM 1: EXAMPLE OF A 5 PANEL UNIT I N S ID E O U TS ID E Panel #1: folding center pivot panel Panel #2: folding center pivot panel Panel #3: folding center pivot panel...
  • Page 4 2. Make sure that all components and hardware, which might be shipped separately do not get lost. As the CSW75 system is a top-hung system, it is essential that a proper substrate with the proper 3. Store in a clean and dry location and protect against...
  • Page 5: Unit Installation

    NANAWALL CSW75 OWNER’S MANUAL panels (i.e. system weight with 12 mm (1/2") tempered 8. For installations into heavy gage, all metal studs must glass app. 8lb/ft ² ) in the opening and in the stacking have wood backing. area (unit in open position).
  • Page 6 The key to having a properly installed and material and construction. If the factory pre-drilled holes operating CSW75 system is to install a perfectly are sufficient, then 8 mm (5/16") diameter screws can be level upper track at the correct height from the used.
  • Page 7 NANAWALL CSW75 OWNER’S MANUAL IMPORTANT: ADJUST EACH ANCHORAGE Step B1 POINT AS NEEDED TO MAKE THE UPPER TRACK Check all the carriers on all the folding panels. Make sure ABSOLUTELY LEVEL AND PLUMB. USE A all the locking nuts are securely tight. Do not make any TRANSIT/LASER AND OTHER SIMILAR PRECISE adjustments on the carriers, yet.
  • Page 8 NANAWALL CSW75 OWNER’S MANUAL Now drill the appropriate size hole for the pivot point. If the gaps are not correct, then adjust the upper track If concrete, use a diamond core drill bit with the proper by removing or adding shims above the head track as diameter size.
  • Page 9 NANAWALL CSW75 OWNER’S MANUAL on the opposite side of the single/double action end Step E2 For the center pivot end panel (non-sliding) with pivot panel (Panel #2) and add blue masking tape underneath point, the dimension for the center of the pivot axle to the the approximate location of the locking bolt.
  • Page 10 NANAWALL CSW75 OWNER’S MANUAL Step E3 Make sure that the full underside of the box rests on a For the offset pivot end panel (non-sliding) with pivot flush and level surface and fix it temporarily into place. point, the dimension for the center of the pivot axle to the Then install the top pivot axle into the top track.
  • Page 11 NANAWALL CSW75 OWNER’S MANUAL floor. Then mark the dimensions of the box on the floor F. FINAL STEPS too; if concrete, cut and chisel out the concrete to recess Step F1 the floor closer into the floor. Position the box at the right Close and lock all panels into position.
  • Page 12 8. For closing, please proceed in reversed order as have it inspected by a NanaWall Certified Installer as described above. To pull the panels from the stacked soon as possible.
  • Page 13 8. It is highly recommended that a maintenance/ Locking points should be gently opened and closed service contract be entered with a NanaWall certified and not forced. Panels should be opened and closed installer, who can clean, lubricate and inspect in the proper manner and sequence.
  • Page 14: Maintenance Checklist

    Ask NanaWall for the glass dimensions. Please note that glass c. Check if all panel end caps are in place is required to be safety glass – either fully tempered or and fixed laminated as specified for a particular order.
  • Page 15 May 1, 2023, to be installed in the United States (excluding territories) or Canada. NanaWall shall have no obligation to respond under this Warranty until receipt of proper notice of a claim and an opportunity to respond. Upon notice and confirmation by NanaWall of a condition covered under this Warranty, NanaWall will respond in good faith and in a timely manner as follows: TEN YEAR COVERAGE.
  • Page 16: Additional Service Information

    Screens. For a screen part (excluding the screen mesh) with a material or workmanship issue that substantially impairs the function of the screen, NanaWall will, at its option, (1) ship a replacement screen or (2) upon return by owner, repair the screen without charge.
  • Page 17 This Warranty may only be modified by a writing signed by an officer of NanaWall. Any action taken by NanaWall does not create a new warranty or extend the duration of the original product warranty. A failure by NanaWall to enforce a warranty provision shall not constitute a waiver barring subsequent enforcement.
  • Page 18 2/3 of the pressure of applicable published test results. • Products or components not supplied by NanaWall; Products that have not been paid for in full; Products ordered in larger sizes or special configurations beyond NanaWall’s published specifications. Product with glass that is heavier than NanaWall specifications;...
  • Page 19 NanaWall Warranty Registration Must be filled out and returned to Nana Wall Systems, Inc., 100 Meadowcreek Drive, Corte Madera, CA 94925 within 30 days from date of purchase of the NanaWall in order for the limited warranty to become effective. ________________________...