Bearing Sensor Cable Installation:
 1.  Ensure that all connectors are clean and free of grease and silicone gel.
 2.  For the Front Bearing Sensor Cable, refer to Steps 3-5; for the Rear Bearing Sensor Cable, refer to Steps 
 3.  Install the 9-pin connector at the Front Bearing Sensor Feedthrough and torque the fasteners to 0.5 Nm 
 4.  Apply a thin coating of dielectric grease to the exterior of the bearing sensor   9 -pin connector where it 
 5.  Install the cable to J10 on the Backplane. Ensure that plug is inserted in correct polarity. Refer to the 
 6.  Install the 9-pin connector at the Rear Bearing Sensor Feedthrough   a nd torque the fasteners to 0.5 Nm 
 7.  Install the ground wire to J11 or J12 on the Backplane.
 8.  Install the cable to J9 on the Backplane. Ensure that plug is inserted in correct polarity. Refer to the 
Figure 4-264 Bearing Cable Orientation
 9.  Install the Service Side Cover. Refer to Section 4.1.3.1   S ervice Side Cover Removal and Installation on 
 10.  Return the compressor to normal operation.
 11.  Verify sensor cable functionality by performing a bearing calibration. Refer to Section 5.3   B earing 

4.30.5 Bearing Sensor Feedthrough Removal and Installation

The following procedure will contain the same steps for either the Front or Rear Bearing Sensor Feedthrough.

4.30.5.1 Bearing Sensor Feedthrough Removal

 1.  Isolate compressor power. 
 2.  Remove the Service Side Cover. Refer to Section 4.1.3.1   S ervice Side Cover Removal and Installation on 
 3.  Wait for the LEDs on the Backplane to turn off. 
 4.  Isolate the compressor and recover the refrigerant according to industry standards. Refer to Section 3.1  
 5.  Remove the Service Side Cover. Refer to Section 4.1.3.1   S ervice Side Cover Removal and Installation on 
6-8.
(0.4 ft.lb.; 4.4 in.lb.).
meets the feedthrough to seal from moisture ingress.
locating keys on the plug and slots in the connector (The Front locating key should be at the left of the 
J10 Backplane clip.). Gently squeeze the connector retainers to snap the connectors in place.
(0.4 ft.lb.; 4.4 in.lb.).
locating keys on the plug and slots in the connector (The Rear locating key should be at the top of the 
J9 Backplane clip.). Gently squeeze the connector retainers to snap the connectors in place. Refer to 
Section 4.30.3   B earing Sensor Verification.
page 54.
Calibration on page 263.
page 54.
Refrigerant Containment on page 41.
page 54.
M-SV-001-EN Rev. H-1/23/2023 Page 239 of 294

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the Turbocor TT Series and is the answer not in the manual?

Questions and answers

Table of Contents

Save PDF