6.3. Commissioning

The main interface:
If you didn't change the work mode of HYD-ES inverter, which means HYD-ES inverter is working in "Auto Mode":
While "PV Production" > "Home Consumption"
If the battery is not full. HYD-ES inverter will charge the battery.
While "PV Production" < "Home Consumption"
If the battery is not flat. HYD-ES inverter will discharge the battery.

6.4. Menu

In the main interface, press "Down" button to enter grid/battery parameters page:
Main Interface
In the main interface, press "UP" button to enter PV parameters page:
Main Interface
SOFAR HYD 3k~6K-ES
Fig 20. Main interface
Press "Down"
1.Grid(V)
2.AC Current(A)
3.Frequency
4.Batt(V)
5.Batt Chrg Curr.
6.Batt DisChrg Curr.
7.State of Charge
8.Batt Cycles
9.Batt Temp.
Press "UP"
1.PV1 Voltage
2.PV1 Current
3.PV1 Power
Copyright © Shenzhen SOFARSOLAR Co., Ltd
24
User manual

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the HYD 4000-ES and is the answer not in the manual?

Questions and answers

This manual is also suitable for:

Hyd 3000-esHyd 5000-esHyd 6000-es

Table of Contents