Step 6 Insert the optical connector into the new optical module.
Step 7 Check the transmission of CPRI signals by observing the status of CPRI0 and CPRI1 indicators.
For details about the status of the indicators, see the ports and indicators on an AAU of related
manuals of RRU hardware descriptions.
Step 8 Take off the ESD wrist strap or ESD gloves, and pack up all tools.
----End
Follow-up Procedure
l
l
l
Issue 01 (2015-01-15)
Place the replaced component into an ESD box or bag. Then, place the ESD box or bag
into a foam-padded carton or the packing box of the new module.
Complete the fault form with detailed information about the replaced component.
Contact the local Huawei office to handle the faulty component.