First Closing Operation - Siemens SION Operating Instructions Manual

Vacuum circuit-breaker 7.2 kv – 17.5 kv, 16 ka – 31.5 ka 24 kv, 16 ka – 25 ka
Hide thumbs Also See for SION:
Table of Contents

Advertisement

Operation
Check functioning of the closing solenoid Y9 and all available shunt
releases by operating them electrically.
If there is a 3AX1103 undervoltage release (Y7): Has the locking screw of
the striker been shifted from position A to B (see "Removing the transport
block from the undervoltage release" on page 48)?
If there are interlocks and a retrofitted key-operated interlock: Check if the
function of the interlocks as per IEC 62271-200 is guaranteed.
Input
with hand crank,
Charging
with motor operat-
ing mechanism
"CLOSE" pushbut-
Closing
ton,
Remote tripping
"OPEN"
Opening
ton,
Remote tripping
58
WARNING
Do not commission the vacuum circuit-breaker if there are malfunctions.
If the malfunctions or the damage cannot be remedied, contact a sales represent-
ative or Siemens Service and, if necessary, send back the vacuum circuit-break-
er.
Position indicator and spring state indicator when charging the closing
spring, closing and opening
Position indicator
pushbut-
* Spring only charged if motor voltage is applied
Fig. 93
Operating element indicators

First closing operation

Note
If an undervoltage release 3AX1103... is fitted, it must be connected to control
voltage for switching operations (mechanical or electrical), as otherwise closing
is not possible.
If all functions have been checked and are OK, switch on the high voltage while ob-
serving all of the safety regulations and operational requirements.
Spring state indicator
*
9229 0025 176 0-
2018-01-18