Pre-Installation Preparation
2.5.

Equipment Room Requirements

Environment
Ensure that the rack is installed away from any source of heat and sparkle. Avoid direct sunlight. The equipment room
should be clear of corrosive gas and organic solvent.
Space
Enough space to install rack should be reserved to facilitate the installation, maintenance, and cooling of rack. In VE
series rack, the front and rear door open at a maximum angle of 135°, the space required to open the rack front and
rear door is shown in
Figure 2-13
(the figure shows 800mm wide, 1200mm deep rack).
• When installing the rack, the specific installation design should be based on the air conditioner
system and air-duct circulating system in the equipment room.
1 6 1 5 m m
1 3 5 °
1 3 5 °
2 3 7 3 m m
1 3 5 °
Figure 2-13 Space required to open the front and rear door of the rack (overlooking, unit: mm)
Ground Smoothness and Weight-bearing Capacity
The product installation floor must ensure the desired level, the maximum deviation is less than 0.6mm/m. The
weight-bearing capacity of the equipment room must be considered before installation due to heavy rack. Generally,
the required weight-bearing of the equipment room is 1000Kg/m
2
. However, the rack's internal bearing equipment is
different and the weight-bearing requirements of the equipment room are also different. To estimate the
requirements, please consult the nearest Vertiv Co., Ltd. office or service center.
Vertiv | VE Series Rack | User Manual

Hide quick links:

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the VE Series and is the answer not in the manual?

Questions and answers

Table of Contents