GE DEH41552 Installation Instruction page 2

Undervoltage release device

Advertisement

2
STEP 3
Cover Modification for Wire Exiting
Perform cover modification as shown in Figure 4.
Remove all debris .
LOAD
END
CUT NOTCH IN RIGHT SIDE
Figure 4 a. Side View of Breaker Cover
LOAD
END
CUT NOTCH IN RIGHT SIDE
Figure 4b. Side View of Breaker Cover
STEP 4
Removing Tie Bar
Use #1 Phillips screw driver to remove the tie bar and
its mounting screws
from right
Figure 5.
Save th e tie bar a nd its mounting screws.
Figure 5.
LINE
END
LINE
END
pole as shown in
STEP 5
5a. Removal of existing barrier
Remove
the
barrier
between
mechanism center pole, as shown in Figure 6a
REMOVAL OF EXISTING BARRIER
Figure 6a.
5b. Installation of Phase Barrier for UVR
Assemble the Phase barrier supplied with kit, as shown
in Figure 6b
BARRIER SUPPLIED WITH KIT
Fi gure 6b.
right
pole
and