Layout Guide Lines:

Hanger Placement:

 First and Last Hanger – Must be placed at least 250 mm from end of system with
a max distance of 500mm allowed.
 Fix point Hanger – 1x per system, centered approximately. All other hangers
must be sliding
 Distance from joints – At least 250mm, max distance of 500mm allowed.

Joint Placement :

Incorrect Installation
* System Length under 70m, no curves *
See installation instruction for step by step
directions.
Joint Cap – Ensure joint caps are installed
correctly and engaged at top, side and bottom. (see
photo)
Placement – ensure hangers are placed in
accordance with the minimum distance of 250mm and
max distance of 500mm.

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the KBHF and is the answer not in the manual?

Questions and answers

Summary of Contents for Vahle KBHF

  • Page 1 KBHF Trouble Shooting Guide * System Length under 70m, no curves * **IMPORTANT: Always disconnect and lock out system from mains/power supply before performing any inspection or installation work ** Layout Guide Lines: Hanger Placement:  First and Last Hanger – Must be placed at least 250 mm from end of system with a max distance of 500mm allowed.
  • Page 2 Conductor Bar Installation:  Visually inspect system to ensure no horizontal or vertical deviation. Conductor bar should be installed precisely aligned to the runway. (See photo) Incorrect Installation Inspection:  Visually inspect each joint to ensure proper connection and engagement of cap. Joint should be smooth and without any burr to avoid damage to collector brush.

Table of Contents