Bravo B409 Installation Instructions Manual

Tank sump with reinforced bottom

Advertisement

Quick Links

S. Bravo Systems, Inc.
2929 Vail Ave. - Commerce, CA 90040
(323) 888-4133 - FAX: (323) 888-4123
www.SBravo.com
Written by: Jonathan Smith
ii-B409-DW-10A

Advertisement

loading
Need help?

Need help?

Do you have a question about the B409 and is the answer not in the manual?

Questions and answers

Summary of Contents for Bravo B409

  • Page 1 S. Bravo Systems, Inc. 2929 Vail Ave. - Commerce, CA 90040 (323) 888-4133 - FAX: (323) 888-4123 www.SBravo.com Written by: Jonathan Smith ii-B409-DW-10A...
  • Page 2: Table Of Contents

    S. Bravo Systems product, the warranty pertaining to these products is immediately void. TABLE OF CONTENTS Filling Bravo Systems Double Wall Products with Brine (saline) solution will void the product warranty. You must use only Bravo-Supplied Interstitial Fluid. WARRANTY ii-B409-DW-10A...
  • Page 3 Bravo-approved. If there is any indication or suspect damage, you must mark the freight paperwork BEFORE PENETRATING FIBERGLASS WALLS ENSURE THAT EACH DOUBLE WALL FIBERGLASS SUMP IS HOLDING VACUUM every DoubleWall Sump. be filled with liquid to any level. ii-B409-DW-10A...
  • Page 4: Dry Fitting Sump & Equipment

    MANOMETER KIT (PER SUMP) - Interstitial fluid - Standard Manometer - Manometer Bracket - Factory-Installed Nylon tubing w/20”Hg Vacuum on interstice w/Combination Pressure/Vacuum Gauge TOTAL HEIGHT 4’ = 5 gal 5’ = 6 gal 6’ = 7 gal 7’ = 8 gal ii-B409-DW-10A...
  • Page 5: A) Installing & Securing

    Visually inspect the parts provided by Bravo Systems for In-transit damage and/or missing parts. Continue to keep the Sump clean of debris throughout your installation process. A.2 - Set your B409 Piping Sump where it must be per site plans. Secure the Sump to avoid movement while penetrating. A.3 - Mark where you will penetrate the Base/Tank Collar wall.
  • Page 6: B) Mantadory Air Integrity Test

    Let cure for a minimum of 4 hours @ or above 75° F. FOR HYDROSTATIC MONITORING - PROCEED TO SECTION C. FOR CONTINUOUS VACUUM MONITORING - The B409 DoubleWall Solid Sump w/Bottom cannot exceed 16” of Mercury. (Vacuum) Follow your vacuum system manufacturer’s installation instructions to install, seal, and monitor the doublewall system with vacuum.
  • Page 7: C) Vacuum / Hydrostatic Filling

    You must cut off the barbed plug and connect the provided Barb & Ball Valve Assembly. Close off the ball valve and prepare the Venturi Vacuum Generator and air supply to be used to fill Sump with liquid. ii-B409-DW-10A...
  • Page 8 Advanced Leak Detection Procedure, then Cut the ball valve assembly from its tubing and connect open end of tubing to Primary manometer. Also unthread the Gauge Assembly and use provided PVC threaded plug to close off open test port fitting. ii-B409-DW-10A...
  • Page 9: D) Advanced Leak Detection Procedure

    Contractors. You would do well to be extremely careful with these DoubleWall products while storing, moving, transporting and Installing these critical environmental components. PROCEDURE of Five [ 5 ] Minutes. CHECK WITH YOUR EQUIPMENT MANUFACTURERS INSTALLATION MANUALS FOR INSTALLATION GUIDELINES AND/OR EQUIPMENT LIMITS REGARDING VACUUM AND PRESSURE LEVELS. ii-B409-DW-10A...
  • Page 10 Even though Bravo DoubleWall product corners and edges are thicker than the rest of the Containment sump, These areas recieve the most supceptable to physical damage by Installing Contractors. You would do well to be extremely careful with these DoubleWall products while storing, moving, transporting and Installing these critical environmental components. CTION IAGRAM ii-B409-DW-10A...
  • Page 11: E) Connecting To Manometer

    Cover the manometer with cap and fasten with wire and lead crimp seal. Remove Entire Gauge Assembly by backing off threaded barb fitting. Install PVC Plug Mark the date and time of test and Fig. E.7 Sensor Cable Cap assembly Continuous Monitoring Interstitial & Leak Detection of Secondary Containment ii-B409-DW-10A...
  • Page 12: F) Concrete & Backfill Guidelines

    When peagravel is in place, use a 3mil or thicker plastic sheet to cover the surface of the peagravel no less than 2 feet away from the sump reducer wall. Secure this plastic barrier to the using duct tape. This prevents concrete from seeping too far down into the peagravel. ii-B409-DW-10A...