16975 09-27-2019 ASSEMBLY MANUAL A Backyard Products Company RIDGEPOINTE 8' x 12' (244 x 366 cm) ACTUAL FLOOR SIZE IS 96 x 141" (243,2 x 358,1 cm) KEEP THIS MANUAL FOR FUTURE REFERENCE I M PO RTA NT ! READ INSTRUCTIONS THOROUGHLY PRIOR TO BEGINNING ASSEMBLY.
Page 4
TOOLS Required Optional Phillips Tool Belt/ Utility Knife Screwdriver Nail Pouch Shingle Blades Drill / Driver 1/8" Drill Bit Tin Snips 1/4" Drill Bit Caulk Gun (for drip edge) 5/16" Drill Bit 1/2" Drill Bit Chalk Line #2 Philips Drive Bit Paint Tools Hammer Nail Gun • gun nails Level Safety Glasses Pencil Ladder Tape Measure Gloves...
Page 5
ADDITIONAL MATERIALS FOUNDATION OR FLOOR MATERIALS • This shed kit includes a complete wood floor system. • This shed kit does not include ANY leveling materials. • See the FLOOR LEVELING section on page 7 for recommended methods and suggested materials to properly level your floor, as this will vary depending on your specific site. COMPLETING YOUR SHED You will need these additional materials: 3-TAB SHINGLES ......6 Bundles 1" GALVANIZED ROOFING NAILS..3 Lbs For shingles. PAINT FOR SIDING ......2 Gallons PAINT FOR TRIM ......2 Quarts Use 100% acrylic latex exterior paint. Use 100% acrylic latex exterior paint. (2) coats recommended. CAULK ..........
Page 6
PARTS IDENTIFICATION AND SIZES Part identification WOOD SIZE CONVERSION CHART letters are stamped on some parts. Treated lumber is stamped: Nominal Board Size Actual Size 2 x 4....1-1/2" x 3-1/2" (3,8 x 8,9 cm) 1 x 4....3/4" x 3-1/2" (1,9 x 8,9 cm) 2 x 3....1-1/2"...
Page 7
PARTS LIST continued... 7/16 x 8 x 12-1/2" (1,1 x 20,3 x 31,8 cm) 2 x 3 x 10-1/2" (5,1 x 7,6 x 26,7 cm) 1 x 4 x 96" (2,5 x 10,2 x 243,2 cm) 2 x 4 x 94-1/2" (5,1 x 10,2 x 240 cm) 3/8 x 14-5/8 x 43-1/8" (1,0 x 37,1 x 109,5 cm) 19/32 x 5-1/2 x 6-5/8" (1,5 x 14 x 16,8 cm) 19/32 x 5-1/2 x 6-5/8" (1,5 x 14 x 16,8 cm) 2 x 3 x 5-1/2" (5,1 x 7,6 x 14 cm) 19/32 x 2-1/2 x 23" (2,5 x 6,3 x 58,4 cm) 19/32 x 2-1/2 x 27-9/16" (1,5 x 6,3 x 70 cm) 19/32 x 2-1/2 x 27-9/16" (1,5 x 6,3 x 70 cm) 3/8 x 8-1/2 x 61-5/16" (1 x 21,6 x 155,7 cm) 19/32 x 3-1/2 x 65-7/8" (2,5 x 8,9 x 167,3 cm) 19/32 x 3-1/2 x 65-7/8" (2,5 x 8,9 x 167,3 cm) 2 x 3 x 68-7/16" (5,1 x 7,6 x 173,2 cm) 7-1/4 x 18-1/4" (18,4 x 46,4 cm) OSB OR WOOD GRAIN 2 x 4 x 68-7/16" (5,1 x 10,2 x 173,2 cm) 19/32 x 2-1/2 x 21" (2,5 x 6,3 x 53,3 cm) 19/32 x 2-1/2 x 49-5/16" (1,5 x 6,3 x 125,3 cm) 19/32 x 2-1/2 x 49-5/16" (1,5 x 6,3 x 125,3 cm) 1-1/4 x 2-1/2 x 69" (3,2 x 6,3 x 175,3 cm) PANEL PARTS LIST NOTE: Panel parts are not stamped.
Page 8
WALL PANELS & DOORS 3/8 x 19-5/8 x 72" 3/8 x 48 x 72" 3/8 x 46-1/8 x 72" (1 x 49,8 x 182,9 cm) (1 x 121,9 x 182,9 cm) (1 x 117,2 x 182,9 cm) LEFT DOOR RIGHT DOOR NAIL BOXES 3" (7,6 cm) BOXES 2" (5,1 cm) BOXES FASTENER/HARDWARE BAG x120 1-1/2" (3,8 cm) NOTE:...
Page 9
FLOOR LEVELING OPTIONS There are multiple ways to level your floor frame. Our recommended leveling method is shown below. Leveling materials are not included in this kit. PREFERRED METHOD - 4x4 TREATED RUNNERS • 3" Screws angled into 4x4. • (2) at each point frame • and 4x4 touch. 12" (30,5 cm) Measurements to centers of 4x4's. MATERIAL REQUIRED 12" 4x4 x 12' (10 x 10 x 366 cm)Treated Lumber (30,5 cm) Fasteners for Frame to 4x4.
Page 10
CONCRETE FOUNDATION Your kit contains all materials to construct a wooden floor. If you choose to install your kit on a concrete slab refer to the diagram below. Treated Sill Plate Caulk between sill plate and concrete. 3-1/2" (8,9 cm) 4" (10,2 cm) Building Size Actual Size 8' x 12' (243,2 x 365,8 cm) 96" x 141" (243,2 x 358,1 cm) 141" (358,1 cm) 96" (243,2 cm) 134" (340,4 cm) Requires: 2 x 4 x 11'-2" (5,1 x 10,2 x 344,5 cm) MUST be treated lumber.
Page 11
FLOOR FRAME PARTS REQUIRED: 3" (7,6 cm) 2 x 4 x 93" (5,1 x 10,2 x 236,2 cm) Look for TREATED 2 x 4 x 48" (5,1 x 10,2 x 121,9 cm) Stamp BEGIN Orient parts as shown on fl at surface. Measure and mark. HINT: Use (2) 3" nails at each mark. For easier nailing stand on frame.
Page 12
LEVEL AND SQUARE FLOOR FRAME Before attaching fl oor decking, it is important to level and square the fl oor frame. A level and square fl oor frame is required to correctly construct your shed. BEGIN See page 7 for the preferred fl oor leveling method. Use level and check the frame is level before applying fl oor panels. Check for frame squareness by measuring diagonally across corners. If the measurements are the same, the frame is square. The diagonal measurement will be approximately 170-9/16" (433,2 cm). When the frame is level and square, secure one side of frame to the 4x4 runners with one fastener at ends of each runner. Move to the opposite end of the frame. Secure the frame to 4x4 runners with (1) fastener at ends of each runner making sure the frame remains square (Fig. A) .
Page 13
FLOOR PANELS PARTS REQUIRED: 2" (5,1 cm) 5/8 x 48 x 96" (1,6 x 121,9 x 243,2 cm) Ensure your floor frame is square by installing one panel and squaring frame. BEGIN Attach the 48 x 96" panel with the rough side up (painted-grid lines side) with the 48" edge and corner flush to the floor frame (Fig A). Secure panel with (2) 2" nails in the corners.
Page 14
FLOOR PANELS PARTS REQUIRED: x124 2" (5,1 cm) 5/8 x 48 x 96" 5/8 x 45 x 96" (1,6 x 121,9 x 243,2 cm) (1,6 x 113,3 x 243,2 cm) Continue installing panels with rough side up (painted grid lines). Position 45" panel in middle of fl oor frame. Use grid lines on panel for 2" nails 6" apart on edges, and 12" apart inside panels. 141"...
Page 15
IMPORTANT! Check the floor frame is level after installing floor panels. Re-level if needed. • The floor should be used as a stable work surface for wall construction. • Organize your assembly procedure during the build process HINT: to avoid over-handling of the walls. Back Wall Right Wall Front Wall Left Wall...
Page 16
SIDE WALL FRAME PARTS REQUIRED: 3" (7,6 cm) 2 x 4 x 46-1/2" (5,1 x 10,2 x 118,1 cm) 2 x 4 x 68" (5,1 x 10,2 x 172,7 cm) 2 x 4 x 94-1/2" (5,1 x 10,2 x 240 cm) BEGIN HINT: For left wall, orient parts on edge on floor. Measure and mark. For easier nailing stand on frame. Use (2) 3" nails at each mark and (4) 3" nails at seams 141"...
Page 17
SIDE WALL PANELS PARTS REQUIRED: 2" (5,1 cm) 3/4" GAUGE 46-1/8 x 72" BLOCK (117,2 x 213,4 cm) Ensure your wall frame is square by installing one panel and squaring frame. Place 46-1/8" x 72" panel onto wall frame flush to top of frame with primed side up as shown. Use the gauge block to mark the 3/4" measurement on the wall stud. Secure panel with (2) 2" nails in the corners (Fig. A). Move to the opposite end. Using the long edge of the panel as a lever move the panel side-to-side until you have a 3/4" measurement on the wall stud. Secure corner with (2) 2" nails (Fig. B).
Page 18
SIDE WALL PANELS PARTS REQUIRED: 2" (5,1 cm) 3/4" GAUGE BLOCK 48 x 72" 46-1/8 x 72" (121,9 x 213,4 cm) (117,2 x 213,4 cm) Place center 48" x 72" panel on frame as shown with primed side facing up. Secure with 2" nails 6" apart on edges and 12" apart inside panel. BEGIN HERE For squareness maintain fl ush Flush...
Page 19
BACK WALL FRAME PARTS REQUIRED: 3" (7,6 cm) 2 x 4 x 68" (5,1 x 10,2 x 172,7 cm) 2 x 4 x 89" (5,1 x 10,2 x 226,1 cm) BEGIN Orient parts on edge on floor. Measure and mark. Secure with (2) 3" nails at each mark. 89"...
Page 20
BACK WALL PANELS PARTS REQUIRED: 2" (5,1 cm) 3/4" GAUGE BLOCK 3/8 x 48 x 72" (1 x 121,9 x 182,9 cm) Install 48" x 72" wall panels with primed side up as shown. Secure panels to frame with 2" nails 6" apart along edges and 12" apart on inside of panel. BEGIN HERE 3-1/2"...
Page 21
FRONT WALL PARTS REQUIRED: 3" (7,6 cm) 2 x 4 x 16-1/2" (5,1 x 10,2 x 41,9 cm) 2 x 4 x 68" (5,1 x 10,2 x 172,7 cm) 2 x 4 x 89" (5 x 10,2 x 226,1 cm) BEGIN Orient parts on edge on floor. Measure and mark. HINT: For easier nailing Use (2) 3" nails at each mark. stand on frame.
Page 22
FRONT WALL PARTS REQUIRED: 3" (7,6 cm) 1-1/4 x 2-1/2 x 69" (3,2 x 6,3 x 175,3 cm) TEMPORARY SUPPORT 2" (5,1 cm) 3/8 x 19-5/8 x 72" (1 x 49,8 x 182,9 cm) Place 19-5/8" x 72" panels onto wall frame flush to SZ with primed side up as shown. Secure panel with (2) 2" nails 6" apart. Install OO as a brace to maintain 56" (142,3 cm) opening. Use (2) 3" screws to attach. For squareness maintain flush 19-5/8"...
Page 23
FRONT WALL PARTS REQUIRED: 3" (7,6 cm) 2 x 3 x 72" (5,1 x 7,6 x 213,4 cm) Center OY on SZ fl ush to edge of panel (Fig. A, B). Secure with (5) 3" screws spaced evenly and screwed-in at an angle. Fig. A Flush Flush to panel edge Fig.
Page 24
RIGHT SIDE WALL INSTALLATION PARTS REQUIRED: 3" (7,6 cm) 1-1/4 x 2-1/2 x 69" (3,2 x 6,3 x 175,3 cm) 3" (7,6 cm) 2" (5,1 cm) BEGIN Center 12' right side wall on the 141" (358,1 cm) fl oor dimension. 1" (2,5 cm) overlap is to the bottom. Use OO as a temporary brace. Secure with (2) 3" screws. 3" (7,6 cm) Screws 1"...
Page 25
BACK WALL INSTALLATION PARTS REQUIRED 2" (5,1 cm) 3" (7,6 cm) 2" (5,1 cm) 1-1/2" (3,8 cm) 3" (7,6 cm) Fig. B BEGIN Place back wall centered on fl oor. Secure wall with (1) 2" screw into side wall 2" (5,1 cm) bottom plate (Fig. A) and top plate (Fig. B). Screw Flush Secure wall to bottom plate fi...
Page 26
LEFT SIDE WALL INSTALLATION PARTS REQUIRED: 2" (5,1 cm) BEGIN Center left side wall on the 141" (358,1 cm) fl oor dimension. Secure wall with (1) 2" screw through back Fig. B wall panel into side wall bottom 2" (5,1 cm) and top plates (Fig. B, Fig. A). Screw Secure wall to bottom plate fi rst. ENSURE PANEL CORNERS ARE FLUSH.
Page 27
LEFT SIDE WALL INSTALLATION PARTS REQUIRED: 3" (7,6 cm) 2" (5,1 cm) 3" (7,6 cm) 1-1/2" (3,8 cm) Nail lower edge of side wall panels to fl oor frame with 2" nails 6" apart. Angle nail to hit fl oor frame (Fig. C). 3" (7,6 cm) Secure wall bottom plates to Nails fl oor with 3" nails (Fig. C). 6"...
Page 28
FRONT WALL INSTALLATION PARTS REQUIRED 2" (5,1 cm) 3" (7,6 cm) 2" (5,1 cm) 3" (7,6 cm) 1-1/2" (3,8 cm) 2" (5,1 cm) Screw Fig. B BEGIN Place front wall on fl oor centered between side walls. Secure wall with 2" screws into top and bottom plates (Fig. A, Fig. B). Flush Secure wall to bottom plate fi rst. ENSURE PANEL CORNERS ARE FLUSH.
Page 29
RAFTERS PARTS REQUIRED: x132 2" (5,1 cm) 3" (7,6 cm) OSB OR WOOD GRAIN 7-1/4 x 18-1/4" (18,4 x 46,4 cm) 2 x 4 x 5-5/8" (5,1 x 10,2 x 14,3 cm) TEMPORARY SUPPORT 2 x 4 x 68-7/16" (5,1 x 10,2 x 173,2 cm) You will build SIX assemblies. (5) with two gussets, and (1) with one gusset. ¸ BEGIN HINT: Place MHA against back wall at measurement shown. Use fl oor and walls to Secure MHA with (2) 3" screws as shown. help assemble rafters! Place two rafter halves PGA in the corner of back and side wall and MHA.
Page 30
RAFTER INSTALL PARTS REQUIRED: 3" (7,6 cm) (1) GUSSET Preassembled Preassembled ¸ BEGIN Secure rafters to top plate with (2) 3" screws in each rafter (Fig. A, Fig. B). Note single-gusset rafter at back wall with gusset facing inward. MEASUREMENTS ARE TO CENTER OF RAFTER Measure to edge of end rafter 22-7/8"...
Page 31
LOFT SUPPORTS PARTS REQUIRED: 3" (7,6 cm) 2 x 4 x 81-1/4" (5,1 x 10,2 x 207 cm) BEGIN Center KOB on back wall top plate, flush to outside of panels (Fig. A). Flush to outside of panel C E N T E Flush C E N T E Flush Flush to panel edge Fig. A Back wall panel Working inside, secure KOB with (4) 3" screws as shown. 3" (7,6 cm) Screws INSIDE OF SHED...
Page 32
LOFT SUPPORTS PARTS REQUIRED: 3" (7,6 cm) 2 x 4 x 94-1/2" (5,1 x 10,2 x 240 cm) Rest UN across side wall top plates. Center UN and measure 3/4" in from edges of top plate (Fig. A). Secure UN to top plates and to rafter with (4) 3" screws. Fig. A Flush 3/4" (1,9 cm) 3" (7,6 cm) Screws FINISH Your loft supports are now installed.
Page 33
LOFT PANEL PARTS REQUIRED: 2" (5,1 cm) 7/16 x 23-1/8 x 82" (1,1 x 58,7 x 208,3 cm) BEGIN Place loft panel onto loft supports centered from side-to-side and fl ush to the back edge of loft support (Fig. A). Secure panel with (16) 2" nails. 23-1/8" x 82" 2" (5,1 cm) C E N T Nails C E N T Flush to...
Page 34
BACK GABLE UNIT PARTS REQUIRED: 1-1/2" (3,8 cm) 2 x 4 x 31-1/4" (5,1 x 10,2 x 79,49 cm) BEGIN Orient JQA on fl at as shown. Place left gable panel as shown. Secure with 1-1/2" nails as shown. 1-3/4" (4,5 cm) 1-1/2" (3,8 cm) Nails Primed side up JQA (on fl at) 5-7/16" (13,2 cm) Place right gable panel fl ush to left panel. Secure with 1-1/2" nails as shown. 1-1/2" (3,8 cm) Nails Primed side up Flush FINISH Your back gable unit is now assembled.
Page 35
BACK GABLE UNIT INSTALLATION PARTS REQUIRED: 1-1/2" (3,8 cm) 3" (7,6 cm) Back Gable Unit BEGIN Install back gable unit on back wall top plate. Measure 1-1/2" down from top plate and mark at each side as shown. Set gable unit on loft deck. Hold secure with (1) 1-1/2" nail on each side. BE SURE GABLE IS CENTERED ON WALL BEFORE NAILING. Continue nailing lower edge of panels into top plate with 1-1/2" nails 6" apart. Secure panels to rafter with 1-1/2"...
Page 36
FRONT GABLE UNIT PARTS REQUIRED: 1-1/2" (3,8 cm) 2 x 4 x 19-1/4" 2 x 4 x 5-5/8" (5,1 x 10,2 x 48,9 cm) (5,1 x 10,2 x 16,2 cm) BEGIN Orient parts HRB and MHA on fl at as shown. Place left gable panel as shown. Secure with 1-1/2" nails as shown. 1-3/4" (4,5 cm) 1-1/2" (3,8 cm) Nails Primed side up HRB (on fl at) Flush MHA (on fl at) 1-1/2"...
Page 37
FRONT GABLE LADDERS PARTS REQUIRED: 3" (7,6 cm) 2 x 6 x 3-5/8" (5,1 x 15,2 x 9,2 cm) 2 x 3 x 68-7/16" (5,1 x 7,6 x 173,8 cm) 2 x 6 x 5-1/4" (5,1 x 15,2 x 13,3 cm) 2 x 3 x 5-1/2" (5,1 x 7,6 x 14 cm) BEGIN Arrange, measure and mark locations of four URB as shown place SXA on top. Secure with 3" screws as shown (Fig. A). Fig. A Ensure parts are flush along edges. 68-7/16" (173,8 cm) 45-3/4"...
Page 38
FRONT GABLE UNIT PARTS REQUIRED: 3" (7,6 cm) 1-5/8" (4,1 cm) Front Gable Unit Ladder Assemblies To complete gable ladder, toe-screw two ladder assemblies together with (4) 3" screws (Fig. F). Fig. F Flush 3" HINT: (7,6 cm) Pre drill to avoid Screws splitting wood. Place gable unit primed side down on gable ladder.
Page 39
FRONT GABLE UNIT INSTALLATION PARTS REQUIRED: 3" (7,6 cm) 2" (5,1 cm) Front Gable Unit BEGIN Install front gable unit on front wall top plate. Measure 1-1/2" (3,8 cm) down from top plate and mark at each side as shown. Set gable unit on top plate. Hold secure with (1) 2" nail on each side. BE SURE GABLE IS CENTERED ON WALL BEFORE NAILING.
Page 40
FRONT GABLE UNIT INSTALLATION 3" (7,6 cm) Ensure the L-blocks are in the correct position using a level, as shown. Secure L-blocks with (2) 3" screws, as shown (Fig. A, Fig. B). HINT: 3" Pre drill to avoid (7,6 cm) 3" splitting wood. Screw (7,6 cm) Screw Fig.
Page 41
FRONT OVERHANG SOFFIT PARTS REQUIRED: 1-1/4" (3,2 cm) 3/8 x 8-1/2 x 61-5/16" (1 x 21,6 x 155,7 cm) Ensure overhang boards meet at peak (Fig. A). BEGIN Position 61-5/16" overhang boards fl ush at peak, primed side down and fl ush to wall panels (Fig A). Secure panels to frame with (20) 1-1/4" screws spaced evenly. Fig. A 1-1/4" (3,2 cm) Screws 16" Center and fl ush (40,6 cm) at peak Approximately Primed Side Down Flush to wall 1-1/4" (3,2 cm) Screws FINISH Your gable overhang soffi ts are installed...
Page 42
SOFFIT NAILERS PARTS REQUIRED: 3/8" x 2" x 5" (1 x 5,1 x 12,7 cm) 2" (5,1 cm) 1 x 2 x 46-3/4" (2,5 x 5,1 x 118,7 cm) 1-1/4" (3,2 cm) 1 x 2 x 96" (2,5 x 5,1 x 243,2 cm) BEGIN At the back of the shed, install 2" x 5" soffi t fi ller fl ush to bottom and outside edges of rafter (Fig. A). Fasten with (2) 1-1/4" screws as shown. Repeat on opposite side. Mark wall at each rafter with a square fl ush to bottom side of rafter and side wall (Fig. B). Install ETB fl ush to ZM and marks.
Page 43
EAVE SOFFIT PARTS REQUIRED: 1-1/4" (3,2 cm) 3/8 x 5-3/16 x 71-1/4" (1 x 13,2 x 181 cm) 3/8 x 5-3/16 x 79-3/4" (1 x 13,2 x 202,6 cm) BEGIN Place 79-3/4" and 71-1/4" soffi t boards primed side down on bottom side of rafter and nailer. Flush soffi t board to front corner of overhang L-block (Fig. A), side wall panels and nailer (Fig. B). screws 12" apart and angled into rafter at seam (Fig. B, Fig. C). Secure with 1-1/4" Repeat steps on opposite side. Fig.
Page 44
ROOF PANELS PARTS REQUIRED: 7/16 x 21 x 23-1/4" 2" (5,1 cm) (1,1 x 53,3 x 59,1 cm) 7/16 x 21 x 96" 7/16 x 21 x 31-3/4" (1,1 x 53,3 x 243,2 cm) (1,1 x 53.3 x 80,6 cm) 3/4" GAUGE BLOCK 7/16 x 48 x 23-1/4" (1,1 x 121,9 x 59,1 cm) 7/16 x 31-3/4 x 48" 7/16 x 48 x 96"...
Page 45
ROOF PANELS PARTS REQUIRED: x216 2" (5,1 cm) 24" 24" 24" 24" Keep spacing between the center of the Fig. C (61 cm) (61 cm) (61 cm) (61 cm) rafters. Secure with (1) 2" nail into each rafter (Fig. C). 2" Nails Flush at peak Fig.
Page 46
ROOF PANELS PARTS REQUIRED: Install roof panels fl ush to installed panels and fl ush to each edge, as shown. 6" (15,2 cm) Install panels in the following order: 1. 31-3/4"x 48" 2. 21"x 96" 3. 21"x 23-7/8" Flush 12" Secure roof panels with 2" nails 6" apart (30,5 cm) along edges and 12"...
Page 47
GABLE FASCIA PARTS REQUIRED: 19/32 x 5-1/2 x 6-5/8" (1,5 x 14 x 16,8 cm) 2" (5,1 cm) TEMPORARY 19/32 x 5-1/2 x 6-5/8" (1,5 x 14 x 16,8 cm) 3/8 x 8 x 12-1/2" (1 x 20,3 x 31,8 cm) 19/32 x 3-1/2 x 65-7/8" (2,5 x 8,9 x 167,3 cm) 19/32 x 3-1/2 x 65-7/8" (2,5 x 8,9 x 167,3 cm) Use shelf brackets as temporary ledger-boards to help install trim boards. BEGIN Install (4) 8 x 12-1/2" projecting out past edge of OSB roof panels, two on each side of roof, as shown. Fasten each with 2" fi nish nails. Do not sink nails completely.
Page 48
FRONT OVERHANG TRIM PARTS REQUIRED: 1-1/4" (3,2 cm) 3/8 x 4-1/8 x 8-1/2" (1,0 x 10,5 x 21,6 cm) BEGIN Position overhang corner soffi ts primed side out and fl ush to trim (Fig. A). Secure corner soffi ts with (4) 1-1/4" screws at each side. Screw into L-block. Fig. A Flush Flush 1-1/4" (3,2 cm) Screws Primed side out Primed side out FINISH Your corner soffi ts are now installed.
Page 49
EAVE FASCIA PARTS REQUIRED: 2" (5,1 cm) 3/8 x 3 x 71-1/4" (1 x 7,6 x 181 cm) 3/8 x 3 x 79-3/4" (1 x 7,6 x 202,6 cm) ¸ BEGIN Install fascia boards fl ush to rafters and fl ush to roof panels (Fig. A). Secure with (2) 2" fi nish nails at each rafter and (4) 2" fi nish nails at seam. Repeat STEP 1 to install fascia on opposite side. 3/8 x 3 x 71-1/4" 3/8 x 3 x 79-3/4" SEAM 3/8 x 3 x 71-1/4"...
Page 50
COLLAR TIES PARTS REQUIRED: 3" (7,6 cm) 2 x 4 x 46-1/2" (5,1 x 10,2 x 118,1 cm) BEGIN Position and level OP on 4th and 6th rafters from back wall. Flush OP to roof panels. HINT: For best appearance install OP on rafter facing away from door. Secure with 3" nails as shown. Flush Flush 3" (7,6 cm)
Page 51
SHELVING PARTS REQUIRED: 2" (5,1 cm) 2 x 3 x10-1/8" (5,1 x 7,6 x 25,7 cm) 3/8 x 8 x 12-1/2" (1 x 20,3 x 31,8 cm) BEGIN Secure AE to bracket panels with (3) 2" nails. Assemble (10) shelf supports as shown; (8) right-side, (2) left-side. Flush 2" (5,1 cm) Nails Flush Flush Secure each shelf support as shown height with (3) 2" nails. 2" (5,1 cm) Nails Flush Corner Stud Flush 55-3/4"...
Page 52
SHELVING PARTS REQUIRED: 2" (5,1 cm) 1-1/4" (3,2 cm) 7/16 x 11-7/8 x 96" (1,1 x 30,2 x 243,2 cm) 1 x 4 x 96" (2,5 x 10,2 x 243,2 cm) Install shelf panels centered over shelf supports. Secure with 1-1/4" screws at each support. 11-7/8"x 96" 1-1/4" (3,2 cm) Flush Screws 11-7/8"x 96" Flush Secure KP with 2" nails at each support as shown. 2" (5,1 cm) Nails Flush FINISH...
Page 53
DOOR TRANSOM WINDOWS PARTS REQUIRED: 3/4" (1,9 cm) Left Door Right Door We recommend painting the doors and door edges edges before installing windows. ¸ BEGIN Fig. A BACK SIDE OF RIGHT DOOR Working fi rst with the right door, measure 1-1/8" from bottom of opening at two locations (Fig. A). Mark each measurement. Scribe a line across door panel. CENTER CENTER Mark center of window opening at top and bottom. 1-1/8"...
Page 54
DOOR TRANSOM WINDOWS PARTS REQUIRED: Fig. A For the left door, measure 1-1/8" from bottom of opening BACK SIDE OF LEFT DOOR at two locations (Fig. A). Mark each measurement. Scribe a line across door panel. CENTER CENTER Mark center of window opening at top and bottom. 1-1/8" 1-1/8" (2,9 cm) (2,9 cm) Place window fl ush to the measured line.
Page 55
DOORS PARTS REQUIRED: 3" (7,6 cm) 1-1/4 x 2-1/2 x 69" (3,2 x 6,3 x 175,3 cm) 1-1/4" (3,2 cm) 1 x 3 x 5" (2,5 x 7,6 x 12,7 cm) Left Door Right Door BEGIN Orient parts as shown on flat surface. 3/8" offset is to top. Look for red (right) and green (left) on hinge board. Attach temporary supports OO and GAA as shown. Tighten securely. 3/8"...
Page 56
DOORS PARTS REQUIRED: 3" (7,6 cm) 1-1/4 x 2-1/2 x 69" (3,2 x 6,3 x 175,3 cm) Install OO fl ush under panels. Secure to fl oor frame with (2) 3" screws (Fig. A) . Fig. A Flush against wall panels Center doors on panel seam as shown (Fig. B) . Screw hinge boards into wall supports and fl oor with (10) 3" screws as shown. Make sure screws go into framing and fl oor (Fig. C) . Remove temporary supports and ensure that the doors open properly. SEAM Fig.
Page 57
DOOR TRIM PARTS REQUIRED: 2" (5,1 cm) 19/32 x 3-1/2 x 66" (2,5 x 8,9 x 167,6 cm) 19/32 x 2-1/2 x 21" (2,5 x 6,3 x 53,3 cm) 3/4" (1,9 cm) 56" Metal Threshold 19/32 x 2-1/2 x 49-5/16" (1,5 x 6,3 x 125,3 cm) 3/4" (1,9 cm) x11 Bagged seperately / special coating 19/32 x 2-1/2 x 49-5/16" (1,5 x 6,3 x 125,3 cm) BEGIN Reinforce the door and install upper horizontal door rails MDA. Flush MDA to bottom of window opening. Secure trim with 3/4" screws from behind door panel into trim (Fig. A, B). Secure window with (2) 3/4" screws through four holes in frame (Fig. B). Attach CTL and CTR with 3/4" screws. Fig.
Page 58
DOOR STIFFENERS PARTS REQUIRED: 2" (5,1 cm) 1-1/4 x 2-1/2 x 69" (3,2 x 6,3 x 175,3 cm) BEGIN Center OO vertically on the left door in the door opening (Fig. A). Offset OO 3/4" (1,9 cm) along the edge of door (Fig. B). Secure with (7) 2" screws through outside trim into OO (Fig. B) Center OO vertically on the right door in the door opening (Fig. A). Offset OO 3/4" (1,9 cm) along the edge of door (Fig. B).
Page 59
DOOR HARDWARE PARTS REQUIRED: 1" (2,5 cm) 5/16" (0,8 cm) Drill Bit BEGIN Place spring bolt onto OO in open position with bolt end 3/8" down from frame. Bolt is open when loop is contacting base (Fig A) . Mark and pre-drill holes for screws. Install bolt with screws supplied and drill 5/16" hole for bolt to extend into. Place bolt onto OO in open position with bolt end 1/2" up from fl oor. Bolt is open when loop is contacting base (Fig B) . Mark and pre-drill holes for screws.
Page 60
DOOR HARDWARE / DECORATIVE HINGES PARTS REQUIRED: 1-1/2" (3,8 cm) 3/8" (10,9 cm) Drill Bit 3/4" (1,9 cm) 1/4" (0,6 cm) Drill Bit BEGIN Measure and mark location of hole on outside of right door as shown (Fig. A) . Pre-drill hole with 1/4" drill. Re-drill hole with 3/8 " drill. Keep drilled hole square to trim to avoid breaking edge of door stiffener. RIGHT DOOR Flush to hinge TOP VIEW 1-3/4" (4,4 cm)
Page 61
GABLE WINDOW PARTS REQUIRED: 1-1/4" (3,2 cm) Gable Window BEGIN Apply high quality exterior-grade caulk behind frame near edge before installing to seal window. From outside of shed, center window in opening and level. Secure with (2) screws into 2x4 gable connectors as shown. 1-1/4" (3,2 cm) Screws Caulk behind frame near edge before installing.
Page 62
GABLE WINDOW TRIM PARTS REQUIRED: 2" (5,1 cm) 19/32 x 2-1/2 x 11-1/2" (1,5 x 6,3 x 29,2 cm) 19/32 x 2-1/2 x 16-1/2" (1,5 x 6,3 x 43,1 cm) Center window trim on window. NOTE: There will be a slight reveal inside window. Secure window trim with (4) 2" finish nails into gable connectors and (8) finish nails into gable panel, as shown. Gable Connector Avoid nailing 2" (5,1 cm) Finish Nails into metal window flange Flush CENTER TRIM ON WINDOW...
Page 63
GABLE WINDOW PARTS REQUIRED: 3/4" (1,9 cm) From inside, secure trim with (8) 3/4" screws. Snip protruding fi nish nails. Do not screw into window fl ange. 3/4" (1,9 cm) Screws INSIDE OF SHED FINISH Your gable window is now installed.
Page 64
CORNER TRIM PARTS REQUIRED: 2" (5,1 cm) 3/8 x 1-3/4 x 70-1/2" (1 x 4,4 x 179,1 cm) 3/8 x 1-3/4 x 67-9/16" (1 x 4,4 x 171,6 cm) ¸ BEGIN Front and back 70-1/2" corner trim is fl ush under gable panel and fl ush along the face of side wall panel. Fasten with 2" fi nish nails spaced evenly. Install 67-9/16" side corner trim fl ush along edge of front corner trim and fl ush up against eave soffi t Fasten with 2" fi nish nails spaced evenly. Repeat STEPS 1 - 2 to install trim to all four corners. FRONT BACK Fig.
Page 65
GABLE DECORATIVE TRIM PARTS REQUIRED: Gable Cleat 19/32 x 2-1/2 x 23" (2,5 x 6,3 x 58,4 cm) 3/4" (1,9 cm) 19/32 x 2-1/2 x 27-9/16" (1,5 x 6,3 x 70 cm) 2" (5,1 cm) 19/32 x 2-1/2 x 27-9/16" (1,5 x 6,3 x 70 cm) BEGIN Position gable decoration primed side facing down on top of BZL and BZR fl ush along edges and at peak. Secure with 3/4" screws. 3/4" (1,9 cm) Primed Side Screws DOWN Flush Flush Primed Side Primed Side DOWN DOWN Flush...
Page 66
HOOK & EYE PARTS REQUIRED: Hook ¸ BEGIN Install hooks into endcap and into L-block behind (Fig. A). Swing door open to locate eye. Fig. A Hook FINISH Your hook and eyes are installed.
Page 67
VENTS PARTS REQUIRED: 1/2" (1,3 cm) 8 x 16" (20,3 x 35,6 cm) You can place your side wall vent on either side of shed ¸ BEGIN Locate and mark for vents in side walls. Install (1) vent near the fl oor and (1) vent near the eave. Caulk behind vent fl anges. Secure with 1/2" screws. Upper Side Wall Vent 3"– 5" (7,6 – 12,7 cm) Caulk 4-1/4"...
Page 68
PAINT & CAULK - NOT INCLUDED - • Use acrylic latex caulk that is paintable. Caulk at all horizontal and vertical seams, between the trim and walls, and all around the door trim. • Use a high quality exterior acrylic latex paint. When painting your building, there are a few key areas that can be easily overlooked that must be painted: • Bottom edge of all siding and trim • Inside of doors and all 4 edges Note: Prime all un-primed exterior wood before painting. (Follow directions provided by manufacturer.) ROOF FELT - NOT INCLUDED - • Install felt flush to all roof edges overlapping 3". Use minimal amount of roofing nails to hold in place. OK to overlap at ridge.
Page 69
SHINGLES - NOT INCLUDED - • Follow directions provided by manufacturer and these instructions. Familiarize yourself with a 3-Tab Shingle. Notch Notch SHINGLE NAIL PATTERN 1/2" 1" Sealing Strip 1" (1,3 cm) (2,5 cm) (2,5 cm) Half A Rain Slot Full Rain Slot NAILS NEVER DRIVE FASTENERS INTO OR ABOVE SEALING STRIPS. BEGIN Install first starter row upside down and color up with a 1" overhang at back and bottom of roof panel. Use (4) nails per shingle. Starter row must be straight and level all the way across with lower edge of roof deck. NOTE: If you have installed drip edge install shingles flush to drip edge.
Page 70
SHINGLES continued... Beginning at front of shed, install first row of shingles with notch at 1" past roof edge or flush with drip edge. Roof Deck FRONT OF BACK OF SHED SHED 1" (2,5 cm) Flush with starter row. Notch - or - Drip Edge Flush with starter row. Notch Install second row of shingles flush at top of first row's rain slots. Ensure 1" overhang or flush to drip edge at front, stagger each row. FRONT OF BACK OF SHED SHED 1" (2,5 cm) Notch Flush with rain slots.
Page 71
SHINGLES continued... Continue installing rows of shingles to the peak. At the peak make sure there is a maximum of 5" or less to the rain slot, as shown below. If shingles overlap at ridge cut to peak with a utility knife. 5"...
Page 72
SHINGLES - RIDGE CAP • You will finish off the top of the roof with a ridge cap made from shingles. BEGIN Cut shingles into THREE pieces. Hint: Use cut-off pieces first. 2" 2" (5 cm) (5 cm 2" 2" 2" 2" (5 cm) (5 cm) (5 cm) (5 cm) Score shingle, then snap-off angled cut. Weather Seal Top of slot. 30 to 32 Note: • You will need about 30 - 32 cut pieces.
Page 73
SHINGLES - RIDGE CAP continued... Continue installing ridge cap to back of roof. Make sure there is 4" between the shingle-color and edge of shingles. 4" (10 cm) Trim cap off fl ush to shingles When you have 4" minimum of shingle color cut one piece to cap your roof. Cut at top of rain slot.
Page 74
LIMITED CONDITIONAL WARRANTY* Backyard Storage Solutions, LLC warrants the following: Every product is warranted from defects in workmanship and manufacturing for 1 year. All accessories, hardware and metal components are warranted for 2 years. All Oriented Strand Board (OSB) is warranted for 2 years Siding and Trim is warranted for 15 years.