NetApp FAS2020 Installation And Setup

NetApp FAS2020 Installation And Setup

Advertisement

Before you begin

1
If you have not already done so, gather the required information and confirm your site
requirements, as described in the Site Requirements Guide at http://now.netapp.com/.

Install in rack

3
Four-post rack
Front rail
(2x)
Clip nut (4x)
Note:
See the rail kit installation flyer included with the rail kit for the two-post procedure.

Cable the system

4
Cable controllers
RJ-45 to DB-9 adapter to console port (required)
1
0a
0b
Console cable to adapter
2
0a
0b
Network cables to e0a and e0b ports
3
0a
0b
Network cable to Remote Management port
4
6
0a
0b
Boot the system and proceed with setup
5
- Turn on the power to your system. It takes the LEDs on your system power supplies a few seconds to illuminate.
- Use the console interface and proceed through the setup questions. See the Data ONTAP Software Setup Guide at http://now.netapp.com/.
Caution:
Use only the NetApp
®
rail kit to install your system. Using a different rail kit can cause injury to you or damage to your system.
(2x)
(2x)
Cable disk shelves
These are a few common configurations. For additional options, see Supported Configurations for
FAS2000-series Systems at http://now.netapp.com.
Port labels
e0a
e0b
Active/Active NAS or ISCSI:
1 Fibre Channel Disk Shelf Stack (Multipath)
Controller to shelf
1
8
Remote
Management
Port
Fibre
Channel
e0a
e0b
8
Ethernet
Console
Shelf to shelf
2
e0a
e0b
8
Shelf to controller
3
e0a
e0b
8
8

Unpack and verify contents

2
Your system comes with an accessory kit that includes the following components:
- This installation poster
- Software license flyer
- Grounding kit
Single Controller Dual Path
Controller to shelf
1
FAS2020
0a
0b
10101
e0a e0b
PSU
PSU
PSU
Controller Module B
FAS2020
0a
0b
10101
e0a e0b
0a
0b
or
DS14
DS14
OUT
IN
PSU
PSU
PSU
IN
IN
OUT
DS14
DS14
OUT
IN
PSU
PSU
PSU
IN
IN
IN
OUT
FAS2020
0a
0b
10101
e0a e0b
PSU
PSU
Controller Module B
0a
0b
10101
e0a e0b
DS14
OUT
IN
PSU
PSU
IN
OUT
DS14
OUT
IN
PSU
PSU
IN
OUT
FAS2020
0a
0b
10101
e0a e0b
PSU
PSU
Controller Module B
0a
0b
10101
e0a e0b
DS14
OUT
IN
PSU
PSU
IN
OUT
DS14
OUT
IN
PSU
PSU
IN
OUT
FAS2020 System
Installation and Setup
- Power cables
- DB-9 to RJ-45 console adapters
- Rail kit (for two-post and four-post racks)
Mounting
bracket
(2x)
Active/Active FC SAN Dual Path
Controller to switch
1
PSU
FAS2020
0a
0b
10101
10101
e0a e0b
PSU
or
Controller Module B
0a
0b
10101
OUT
IN
PSU
DS14
OUT
OUT
PSU
IN
OUT
OUT
IN
DS14
PSU
OUT
OUT
PSU
IN
OUT
2
Controller to shelves
FAS2020
0a
0b
10101
PSU
Controller Module B
0a
0b
10101
DS14
OUT
PSU
IN
OUT
DS14
OUT
PSU
IN
OUT
Copyright © 2010 NetApp, Inc. All rights reserved.
2U
3U
3U
Setting the disk shelf IDs
Shelf ID
switch
Note: The disk shelf IDs for the
disk shelves should be set in the
range 1 to 6.
Connect power
Note:
You do not need to
ground your system.
e0a e0b
PSU
e0a e0b
IN
PSU
IN
PSU
e0a e0b
PSU
e0a e0b
IN
PSU
IN
PSU
210-03961+D0

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the FAS2020 and is the answer not in the manual?

Questions and answers

Summary of Contents for NetApp FAS2020

  • Page 1 - Turn on the power to your system. It takes the LEDs on your system power supplies a few seconds to illuminate. - Use the console interface and proceed through the setup questions. See the Data ONTAP Software Setup Guide at http://now.netapp.com/.
  • Page 2 LIFTING HAZARD Shut down the target controller module (called a “node” in an For hot-swappable FRUs: active/active configuration) by completing the applicable 30 kg Always consult http://now.netapp.com for procedure: (67 lbs) current field-replaceable unit (FRU) If you have an active/active configuration replacement procedures.

Table of Contents