EXAMPLE OF NORMAL SYSTEM OPERATION

Upon initial application of AC voltage, the LCD located on upper enclosure will display 'Shutdown'
for approximately 15 seconds. Once the system has finished initializing, the PV-30208 will remain in
standby until adequate PV voltage is available. 5 minutes after the PV start voltage has been reached,
the PV-30208 will synchronize to the utility grid and begin peak power tracking the PV array. The time
delay protects the inverter from excessive on/off cycling.
The PV-30208 will continue to process power until the AC output power approaches the operating
losses of the inverter for a period of 5 minutes. The time delay protects the inverter from excessive on/
off cycling.
PV-30208 Photovoltaic Inverter
4-6
DOCUMENT: 151315
Operation and Maintenance Manual
Copyright 2003, Xantrex Technology