Nestle® Vitality® Express — Extended Shutdown and Startup Procedure Please follow all instructions to sanitize and shutdown the Nestle® Vitality® Express juice dispenser when placing the machine out of commission for extended periods (more than 1 week). For Shutdown: 1. Open the front door.
Page 2
For Startup: 1. Plug in the dispenser to power up and turn on the water supply. Confirm the drip tray and drip tray screen are in place. 2. Insert thawed concentrate containers. Dispense product out of each nozzle and taste to ensure unit is functioning properly. If you have any questions, please do not hesitate to call:...
Page 3
NESCAFÉ® Black 3S, 2/120 and 1/40 Liquid Coffee Machines — Extended Shutdown and Startup Procedure Please follow all instructions to sanitize and shutdown the NESCAFÉ® Black 3S, 2/120 and 1/40 Liquid Coffee Machines when placing them out of commission for extended periods (more than 1 week). For Shutdown: 1.
Page 4
For Startup: 1) Turn on the water valve in the back of the machine and plug in the dispenser. 2) Once it has heated, we can proceed to clean the machine to prepare it for dispensing. 3) Dispense hot water for 15 seconds into a pitcher and discard. 4) Finally, insert product bag(s) into the compartments.
NESCAFÉ® Mini XL — Extended Shutdown and Startup Procedure Please follow all instructions to sanitize and shutdown the NESCAFÉ® Mini XL coffee dispenser when placing the machine out of commission for extended periods (more than 1 week). For Shutdown: 1. Open the front door. 2.
Page 6
For Startup: 1. Turn water on at main shutoff going to machine. 2. Make sure drip tray is installed. 3. Turn power on at the on/off button inside the machine. 4. Open the front door. 5. Turn the canister chutes in the up position. 6.
NESCAFÉ® Bean-to-Cup Coffee Machine — Extended Shutdown and Startup Procedure Please follow all instructions to sanitize and shutdown the NESCAFÉ Bean-to-Cup Coffee Machine when placing them out of commission for extended periods (more than 1 week). For Shutdown: 1. Open the front door. 2.
Page 8
For Startup: 1. Plug in the dispenser to power up, and turn on water supply. 2. Once the dispenser is ready, tap on any drink to see the five icons on the top panel. Tap on the water drop icon and this will give you the option to rinse the bowls and brewer chamber to get the dispenser ready for dispensing.
Page 9
Nestle® Vitality® Express Touch — Extended Shutdown and Startup Procedure Please follow all instructions to sanitize and shutdown the Nestle® Vitality® Express Touch juice dispenser when placing the machine out of commission for extended periods (more than 1 week). For Shutdown: 1.
Page 10
For Startup: 1. Plug in the dispenser to power up and turn on the water supply. Confirm the drip tray and drip tray screen are in place. 2. Insert thawed concentrate containers. Dispense product out of each nozzle and taste to ensure unit is functioning properly. If you have any questions, please do not hesitate to call:...
Page 11
NESCAFÉ® 8/100 — Extended Shutdown and Startup Procedure Please follow all instructions to sanitize and shutdown and start up the NESCAFÉ® 8/100 coffee dispenser when placing the machine out of commission for extended periods (more than 1 week). For Shutdown: 1.
Page 12
For Startup: 1. Turn water on at main shutoff going to machine. 2. Make sure drip tray is installed. 3. Turn power on at the on/off button in back of machine. 4. Open the front door. 5. Turn the canister chutes in the up position. 6.
Need help?