MAINTENANCE - OIL CHANGE
IMPORTANT: OIL CHANGE SCHEDULE
THE GEARBOX OIL CAPACITY IS ENGRAVED ONTO THE SERIAL TAG LOCATED ON THE SIDE OF THE SLASHER.
Initial (Bed-in) oil change:
The first oil change must be carried out within the first 30 hours of operation. Thereafter, every 300 hours.
The first oil change must be carried out within the first year of operation. Thereafter, every 3 years.
FIRST OIL CHANGE
2ND OIL CHANGE PLUS SUBSEQUENT OIL CHANGES
SLASHER MODEL
1250MM MULTIFIT (SL-000227)
1250MM SLIDE SHIFT FRAME (SL-000225)
1500MM MULTIFIT (SL-000002)
1500MM SIDE SHIFT SLIDE FRAME (SL-000103)
1500MM EXCAVATOR MOUNT (SL-000153)
1500MM SIDE SHIFT SLIDE FRAME C/W EXCAVATOR MOUNT (SL-000165)
1500MM SIDE SHIFT FRAME (SL-000267)
1800MM MULTIFIT (SL-000170 / SL-000255)
1800MM SIDE SHIFT SLIDE FRAME (SL-000228)
1800MM MULTIFIT HEAVY DUTY PICK UP (SL-000283)
This symbol only refers to slashers which use a planetary drive gearbox.
With all slashers, to inspect and change the oil is recommended to be done by a Digga Authorised Service Agent.
Howerever if that is not possible, please refer to the Digga document PM-000151.
PM-000084-D - Slasher Operators Manual - OCTOBER 2017
18
SLASHERS WITH GEARBOX
Within the first 30 hours of use
After 300 hours of use thereafter
OIL TYPE
CASTROL ALPHASYN EP 320
(SYNTHETIC)
OR EQUIVALENT
CASTROL ISO SP 320
(MINERAL)
OR EQUIVALENT
This symbol only refers to slashers which are direct drive units.
SLASHERS WITH DIRECT DRIVE
Within the first year
Every 3 years thereafter
OIL QTY (ml)
650 ml
250 ml

Advertisement