WIND TECHNOLOGY V1.06.18 1. INTRODUCTION Objective This manual is to describe the installation and maintenance processes of the E200 wind turbine to ensure correct installation and commissioning. Also making known a little bit of the Enair company. About Enair Enair works with the illusion of collaborating in the transition to a sustainable energy model, which increasingly have more in weight renewable energy and distributed generation.
For this reason, it is necessary that before carrying out any installation, the personnel responsible for it, acquire the necessary knowledge. Only qualified personnel should install or operate the Enair wind turbine. When the rotor/nacelle is accessed, the wind turbine must be in emergency stop.
Page 6
Indirect contact with elements that are accidentally live due to an installation fault. Ensure that the drive is earthed to ensure protection against indirect contacts. If during the installation or operation process, questions or doubts arise, you can contact Enair through the following channels: Tel: +34 96 556 00 18 Email: info@enair.es...
WIND TECHNOLOGY V1.06.18 3. ABOUT SMAL WIND TURBINE ENAIR 200 ENAIR is a wind turbine belonging to the mini wind turbine sector with simple operation and easy assembly. The Wind Turbine works downwind and the orientation is passive through the aerodynamics of the blades.
The brands currently tested by Enair are: Fronius, SMA, Solis and Aros-Rielo. However, the inverter in these wind turbines will always be supplied by Enair, in order to guarantee compatibility with the wind turbine as well as with the standards applicable in each country.Las directivas aplicadas normalmente en los inversores...
The warranty claims set forth herein do not cover the transport costs of the wind turbines or defective elements, derived from the return to ENAIR ENERGY S.L. It also does not cover the costs of intervention arising from the disassembly of the defective equipment, nor does it cover Avenida de IBI, 44 –...
Page 10
180 days from the date of receipt. If ENAIR ENERGY S.L. determines that the problem with the wind turbine is not due to a material or manufacturing defect, the Customer shall be responsible for the costs of carrying out the tests and processing.
WIND TECHNOLOGY V1.06.18 7. PACKING LIST The Enair E200 wind turbine comes in its complete purchase in 4 packages, 2 packages are the whole of the wind turbine plus blades, another is the control system and the remaining is the tower.
Dinamometric since 200Nm 3m textile sling Shackles for tying shackles Recomendaciones Cordless drill with adjustable torque Avenida de IBI, 44 – P.O. 182-03420 | Castalla (Alicante), España P a g e | 12 www.enair.es +34 96 556 00 18 info@enair.es...
Textile sling de 6m Textile sling 0.6m Recomendaciones Cordless drill with adjustable torque Torque wrench up to 72Nm Avenida de IBI, 44 – P.O. 182-03420 | Castalla (Alicante), España P a g e | 13 www.enair.es +34 96 556 00 18 info@enair.es...
7.3.2 Mounting tolos control box: Tools Quantity Screwdriver Star screwdriver Universal pliers Cutting pliers Recomendations Cordless drill with adjustable torque Avenida de IBI, 44 – P.O. 182-03420 | Castalla (Alicante), España P a g e | 14 www.enair.es +34 96 556 00 18 info@enair.es...
V1.06.18 8. INSTALLATION The installation process may vary depending on the type of tower selected, for the Enair 200 wind turbine, several types of towers are available. These can be square lattice, tubular or cable- stayed. For the explanation of the manual we selected the option of lattice towers because it is the standard model.
Page 16
For this work 2 people are recommended, plus the help of the crane. Avenida de IBI, 44 – P.O. 182-03420 | Castalla (Alicante), España P a g e | 16 www.enair.es +34 96 556 00 18 info@enair.es...
Page 17
Avenida de IBI, 44 – P.O. 182-03420 | Castalla (Alicante), España P a g e | 17 www.enair.es +34 96 556 00 18 info@enair.es...
Page 18
Each cable is labeled unequivocally both at the tip of the cable to be connected, and at the connection terminal. Avenida de IBI, 44 – P.O. 182-03420 | Castalla (Alicante), España P a g e | 18 www.enair.es +34 96 556 00 18 info@enair.es...
V1.06.18 9. TRASNPORT 20ft container A complete Enair 200 wind turbine is located in a 20-foot container with the lattice tower included and completely disassembled. Avenida de IBI, 44 – P.O. 182-03420 | Castalla (Alicante), España P a g e | 20 www.enair.es...
25 years. Maintenance works: The components of the ENAIR 200 must only be handled by competent technical personnel. Under no circumstances will unqualified personnel be responsible for maintenance operations, unless directly directed by a qualified technician.
Page 22
10- Change the tubes of hydraulic Every 4 years (indicative) Every 4 years (indicative) power station. Avenida de IBI, 44 – P.O. 182-03420 | Castalla (Alicante), España P a g e | 22 www.enair.es +34 96 556 00 18 info@enair.es...
Page 23
In case of any crack or surface damage due to a collision, you must putty and paint with the recommended paint. Edge of attack Paint inspection Inspect the entire exterior surface of the ENAIR. If necessary, repaint. Características de la pintura White Paint Polyurethane paint, RAL 9003...
Page 24
Torque Socket wrench of 21 - 127 Nm See Appnedix 3, for torque details. Torque wrenches Avenida de IBI, 44 – P.O. 182-03420 | Castalla (Alicante), España P a g e | 24 www.enair.es +34 96 556 00 18 info@enair.es...
Page 25
- ISO 6743 HM - MIL-L24459 Required about 500gr. Tools: Standard grease nipple for grease nipples. Avenida de IBI, 44 – P.O. 182-03420 | Castalla (Alicante), España P a g e | 25 www.enair.es +34 96 556 00 18 info@enair.es...
Page 26
Norm ASTM D1478. Caution: the hydraulic unit oil and sleeves must be changed every 4 years. Avenida de IBI, 44 – P.O. 182-03420 | Castalla (Alicante), España P a g e | 26 www.enair.es +34 96 556 00 18 info@enair.es...
Page 27
Fast connectors: Visual check of the integrity and tightness of the quick connectors. Avenida de IBI, 44 – P.O. 182-03420 | Castalla (Alicante), España P a g e | 27 www.enair.es +34 96 556 00 18 info@enair.es...
Page 28
Annex 3. Avenida de IBI, 44 – P.O. 182-03420 | Castalla (Alicante), España P a g e | 28 www.enair.es +34 96 556 00 18 info@enair.es...
Page 29
Surface inspection: Inspect the entire surface of the tower for corrosion, open welds or bent profiles. Avenida de IBI, 44 – P.O. 182-03420 | Castalla (Alicante), España P a g e | 29 www.enair.es +34 96 556 00 18 info@enair.es...
Page 30
WIND TECHNOLOGY V1.06.18 ANNEX 1 Tower details. Avenida de IBI, 44 – P.O. 182-03420 | Castalla (Alicante), España P a g e | 30 www.enair.es +34 96 556 00 18 info@enair.es...
Page 31
Avenida de IBI, 44 – P.O. 182-03420 | Castalla (Alicante), España P a g e | 31 www.enair.es +34 96 556 00 18 info@enair.es...
Page 32
+ tower apply to the tower. All towers not supplied by Enair must be factory approved and must be accompanied by their dynamic calculation memory.
Page 33
15.70 2.67 14.60 ENAIR recommend use always the K=8 values Note: In addition to the above measurements, the foundation should protrude 0.2m above ground level to prevent the effect of moisture on the base of the tower. Avenida de IBI, 44 – P.O. 182-03420 | Castalla (Alicante), España...
Page 34
WIND TECHNOLOGY V1.06.18 ANNEX 2 – Basic connection scheme Avenida de IBI, 44 – P.O. 182-03420 | Castalla (Alicante), España P a g e | 34 www.enair.es +34 96 556 00 18 info@enair.es...
Page 35
WIND TECHNOLOGY V1.06.18 ANNEX 3 – Torque table * in red the torque more used in the small wind turbine Enair 200. Avenida de IBI, 44 – P.O. 182-03420 | Castalla (Alicante), España P a g e | 35 www.enair.es +34 96 556 00 18 info@enair.es...
Need help?
Do you have a question about the E200 and is the answer not in the manual?
Questions and answers