Download Print this page
GRIPPLE GS10 Installation Manual

GRIPPLE GS10 Installation Manual

Seismic cable bracing

Advertisement

Quick Links

CABLE BRACING INSTALLATION GUIDE
(READ INSTRUCTIONS IN THEIR ENTIRETY BEFORE STARTING INSTALLATION)
Attachment to structure. Gripple cable end fitting
(Eyelet, Standard bracket, or Double Bracket).
Select bracket based on anchor diameter.
Break strength
certified, pre-stretched
Gripple Seismic Cable
Hanger rod
Gripple Seismic
with stiffener
Fastener
as required,
(GS10, GS12,
or equipment
GS19, GS25)
attachment
Attachment to equipment/strut.
Gripple GSS or GSR Bracket.
Select size based on hanger rod
diameter.
GRIPPLE
SEISMIC
®
GS10
(Eyelet or Bracket)
Color coded tag
(see Side 2 for
details)
Brace angle
30º - 60º
IMPORTANT INFORMATION:
a.) Each cable brace should be
b.) Ensure that suitable rod
Gripple Seismic Cable End Fittings:
GS12
(Eyelet or Bracket)
(Single Bracket)
at an angle between 30-60
degrees to the horizontal, as
shown in drawing at left; 45
degrees is optimal.
stiffener is used to prevent
buckling or bending of the
rod in the event of an
earthquake.
GRIPPLE INC.
1611 EMILY LANE
AURORA, IL 60502 USA
Phone: 1-630-406-0600
www.grippleseismic.com
GS25
GS19
(Double Bracket)
INSTALLATION INSTRUCTIONS:
1.) Install Gripple Seismic end fitting
(Eyelet or Bracket for GS10 or GS12;
Single Bracket for GS19, or Double
Bracket for GS25, as shown above)
to structure.
2.) Loosen the nut on the rod hanger and
slot the Gripple Seismic Retrofit Bracket
onto the rod. Tighten the nut onto the
Gripple Seismic Retrofit Bracket.
Ensure that the appropriate washer
per the cable & bracket system being
used is installed and the nut is
tightened down securely onto the
bracket.
3.) Thread free end of cable through first
channel of the Gripple Seismic fastener.
4.) Thread free end of cable through the
hole in the Gripple Seismic bracket.
5.) Position the Gripple Seismic fastener
up the cable so that it is a min. of 12
inches above the bracket. Thread the
remaining cable through the second
channel in the Gripple Seismic fastener
to form a loop around the bracket.
Pull the tail end of the cable to create
a tight loop, and remove the slack
from the Gripple Seismic cable brace.
Use the Gripple supplied Tightening
Tool for the GS19 and GS25 systems.
6.) Trim the tail end of the cable but leave
a minimum tail length of 2 inches.
Install the locking bolts and ensure
that they are tightened down securely.
Ensure that locking bolts are removed
before trying to remove further slack
from the cable or adjust the position of
the Gripple Seismic fastener along the
cable length.
DATE:
3/14/2013
PAGE:
1 / 2

Advertisement

loading
Need help?

Need help?

Do you have a question about the GS10 and is the answer not in the manual?

Questions and answers

Summary of Contents for GRIPPLE GS10

  • Page 1 INSTALLATION INSTRUCTIONS: IMPORTANT INFORMATION: 1.) Install Gripple Seismic end fitting a.) Each cable brace should be (Eyelet or Bracket for GS10 or GS12; at an angle between 30-60 Single Bracket for GS19, or Double degrees to the horizontal, as Bracket for GS25, as shown above) shown in drawing at left;...
  • Page 2 (READ INSTRUCTIONS IN THEIR ENTIRETY BEFORE STARTING INSTALLATION) MAX SYSTEM DESIGN STRENGTHS (LRFD): DOUBLE STACKING: BRACE SIZE: COLOR CODE: LRFD: Gripple Seismic Brackets can be GS10 350 lbs double stacked as shown. (5/64” cable) (158 kgs) Ensure that each bracket is in line...

This manual is also suitable for:

Gs12Gs19Gs25