COMMISSIONING

General commissioning procedure
Clean the connection zone (remove material residues and dirt).
Before commissioning the device check that all screw and terminal connections are tight.
Check that all the cable glands that are not in use have been properly sealed with blind plugs or
blind glands.
Switch on the supply voltage. After the self-test, the status LED (LED bar) must be lit in blue after
15-20 seconds.
Conduct the specified initial tests to comply with local regulations and laws.
Connect the Wallbox terminal panel cover if it has been opened. See section entitled
termination panel
Install the housing cover, see section entitled
Commissioning mode/Self-test
The Wallbox can be set to a commissioning mode to help with the initial system tests. This conducts
a self-test on the device (interlock, contactor actuation, current measurement, etc.) and any errors are
displayed.
After the test has been successfully completed without a vehicle connected, the contactor will be
actuated for a limited period of time (around 10 minutes) to allow the initial tests to be completed. A
normal charging cycle is not possible in commissioning mode.
If the Wallbox is switched on in commissioning mode using the supply voltage, an error (white-red-red-
red) will be displayed for safety reasons to prevent accidental activation.
Enabling the commissioning mode
1. Set DIP switch DSW2.8 to ON.
2. Reset the Wallbox. To do this, press the Service button for 1 second (signal tone).
Commissioning mode is now enabled and is indicated by the status LED being lit in orange.
3. It is now possible for approximately 10 minutes to contact with the measuring instrument using
standard test clips (for example Astaco® test clips from BEHA) and conduct the required safety
tests. After this time the contactor is disabled and the Wallbox switched off.
Disabling the commissioning mode
1. Set DIP switch DSW2.8 to OFF again.
2. Conduct a reset of the Wallbox. Press the Service button for 1 second (signal tone) for this
purpose or switch the supply voltage off and on again. The Wallbox will power up in operating
mode and is then ready for use.
34
cover.
Installing the housing
Installing the
cover.

Hide quick links:

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the i Wallbox and is the answer not in the manual?

Questions and answers

Table of Contents