4 Replacing the Components in the OMB
Figure 4-17 Disconnecting cables
Step 5 Loosen the M4 screw on the panel, and then remove the AC surge protection box, as shown in
Figure
Figure 4-18 Removing the AC Surge Protection Box
Step 6 Install the new AC surge protection box, tighten the screw on the panel until the tightening torque
reaches 1.2 N·m, and then reconnect the cables.
Step 7 Power on the base station.
Step 8 Take off the ESD wrist strap or gloves, and then pack up all the tools.
----End