11. Installation Instruction 11.1 Select the Best Location 11.1.3 Indoor/Outdoor Unit Installation Diagram 11.1.1 Indoor Unit Do not install the unit in excessive oil fume area such as kitchen, workshop and etc. There should not be any heat source or steam near the unit.
11.2 Indoor Unit 11.2.1 How to Fix Installation Plate The mounting wall shall be strong and solid enough to prevent if from the vibration. The center of installation plate should be at more than at right and left of the wall. The distance from installation plate edge to ceiling should more than From installation plate left edge to unit’s left side is From installation plate right edge to unit’s right side is...
Page 4
11.2.3 Indoor Unit Installation 11.2.3.1 For the right rear piping 11.2.3.2 For the right bottom piping 11.2.3.3 For the embedded piping (This can be used for left rear piping and bottom piping also.)
Page 5
11.2.4 Connect the Cable to the Indoor Unit 1. The inside and outside connection cable can be connected without removing the front grille. 2. Unscrew the conduit cover and fix the conduit connector to conduit cover with lock nut, then secure it against chassis.
Page 6
11.2.5 Wiring Stripping and connecting requirement 11.2.5.1 Cutting and flaring the piping Please cut using pipe cutter and then remove the burrs. Remove the burrs by using reamer. If burrs are not removed, gas leakage may be caused. Turn the piping end down to avoid the metal powder entering the pipe.
11.3 Outdoor Unit 11.3.1 Install the Outdoor Unit After selecting the best location, start installation according to indoor/outdoor unit installation diagram. Fix the unit on concrete or rigid frame firmly and horizontally by bolt nut (ø13/32"). When installing at roof, please consider strong wind and earthquake. Please fasten the installation stand firmly with bolt or nails.
11.3.2.3 Connecting the piping to outdoor multi Decide piping length and then cut by using pipe cutter. Remove burrs from cut edge. Make flare after inserting the flare nut (locate at valve) onto the copper pipe. Align center of piping to valve and then tighten with torque wrench to the specified torque as stated in the table. 11.3.2.4 Gas Leak Checking Pressure test to system to 400 PSIG with dry nitrogen, in stages.
8. Mount valve caps onto the 2-way valve and the 3-way valve. Be sure to check for gas leakage. 11.3.3.1 Connect the Cable to the Outdoor Unit 1. Remove Top panel. 2. Remove Control Board Cover (Resin and Metal). 3. Remove Plugs. 4.