(Optional) Connecting the Air Duct
3.5
• An air duct needs to be prepared
onsite based on site requirements.
• When fixing the equipment to the
floor, place the bottom of the air
duct on the floor and use anchor
baffle plates to secure the air duct.
• If the equipment is to be secured to
the base, it is recommended that
you install baffle plates on the base
before securing the bottom of the
air duct.
• Remove the eight screws from
both sides of the equipment.
• Use M4x12 screws to secure the
air duct to the top of the
equipment, and use M6x25
screws to secure the both sides of
the air duct to the both sides of
the equipment.
4
Installing Pipes
4.1
Pipe Layout
1. A 1:100 tilt should be reserved for the
drainpipe and humidifier water inlet pipe.
2. Keep a clearance of at least 25 mm between
pipes. Secure the pipes to supports every a
certain distance.
3. Clean the water inlet engineering pipes to
avoid impurities entering into the humidifier.
4. A reducing valve must be installed if the inlet
water pressure exceeds 0.7 MPa.
5. Pipes should be wrapped with thermal
insulation foam along the route.
4.2
Connecting the Drainpipe
Both hoses and rigid pipes can be connected. This section uses rigid pipe
connection as an example.
(1) Maintenance door
Pipe
support
4
Unit: mm