Connecting Cables - Huawei FusionCol8000-E240 Quick Manual

Modular indirect evaporative cooling system
Hide thumbs Also See for FusionCol8000-E240:
Table of Contents

Advertisement

The example describes how to install an indoor
air supply duct in the FDC scenario.
The entire air duct must be wrapped with thermal
insulation foam. The thickness of the thermal
insulation foam must be at least 3 cm.
The joint between the air duct and the unit
should be sealed to prevent air leakage.
Generally, sealing form should be applied to the
flange edge of the air duct or sealant should be
applied to the flange edge after installation.
8

Connecting Cables

Cable Route
FDC Scenario
Connecting Signal Cables and Power Cables
8.1
1.
Connect signal cables.
Signal cable
terminal
(using X501 as
an example)
Building Scenario
(1) Power cable
(2) Exhaust air damper cable
(3) Supply air damper cable
(4) Electric heater controller cable
(5) Signal cable
If a water sensor (rope type) is
connected, connect the signal cable
to the X201 and X202 terminals.