FusionModule1000A40 ICT Solution
Maintenance Guide
Figure 4-4 Installing a battery pack
Step 6 Connect cables to the rear of the battery pack, and switch on the circuit breaker.
----End
Follow-up Procedure
Dispose of the removed batter pack that is confirmed faulty.
4.1.7 Replacing a Light
Prerequisites
Spare LED lights of the same model are available and functional.
Impact on the System
None
Preparations
Tools: multimeter
Material: spare light
Documents: none
Skill requirement: electrician's work permit
Procedure
Step 1 Locate a failed light.
Issue 01 (2019-03-05)
If a light does not work but the cables to the light are intact, the light has failed and needs
to be replaced.
Copyright © Huawei Technologies Co., Ltd.
4 Parts Replacement
54