Prerequisites

This chapter describes the prerequisites for step–by–step configuration and com-
missioning.
The configuration and commissioning steps are described in detail in Chapters 3
and 5.
2.1

Hardware and software components

In our example, a drive unit is to be assembled for a motor.
The following components are required for the drive unit:
S Active Line Module
S Control Unit CU320
S Motor Module
S Sensor Module SMC20
S Synchronous motor (e.g. 1FK6) or induction motor (e.g. 1PH7) with sensor
S DRIVE–CLiQ cables
You will also need line filters, line reactors for the Active Line Module, motor,
power, and encoder cables, as well as a SITOP modular 24 V DC power supply,
for example.
The following prerequisites must be fulfilled before you start commissioning:
S The CompactFlash Card with firmware must be inserted.
S The components are wired by means of DRIVE–CLiQ
S The PROFIBUS interface Control Unit is connected to a PC/PG via a
PROFIBUS interface
S The STARTER commissioning tool must be installed on your PC/PG.
Note
For instructions on wiring the components, connecting the PROFIBUS interface to
a PC/PG, and installing the STARTER commissioning tool, see the Equipment
Manuals /GH1/ and /GH2/ and the Commissioning Manual /IH1/.
 Siemens AG 2006 All rights reserved
SINAMICS S120 Getting Started with the STARTER Commissioning Tool – 03/2006 Edition