Sequence Of Operation; Outline - Canon imageCLASS LBP6780dn Service Manual

Hide thumbs Also See for imageCLASS LBP6780dn:
Table of Contents

Advertisement

2
Technology > Sequence of Operation > Outline

Sequence of Operation

Outline

The operation sequence is controlled by the DC Controller in the engine control system.
Operations for each period of a print operation from the machine is turned on until the motor
stops rotating are described below.
Period
Duration
WAIT
From the time power switch is
turned on or the dooe is closed
unitil the printer gets ready for a
print operation.
STBY
From the end of WAIT or LSTR
(Standby)
period until either the print
command is received the main
controller or the power switch is
turned off.
INTR
From the time print command is
(Initial rotation)
received from the main controller
unit the temperature of the
fixing unit reaches its targeted
temperature.
PRINT
From the end of INTR period unit
the last media completes the fixing
operation.
LSTR
From the end of PRINT period unit
(Last rotation)
the motor stops rotationg.
2
Technology > Sequence of Operation > Outline
Operation
Brings the printer to printable condition.
The rpinter performs the following during this
period:-Detects cartridge presence.
Maintains the printer in printable condition.
Starts up each high-voltage biases, laser
scanner and fixing unit in preparing for print
operation.
Forme the image on the photosensitive drum
based on the VIDEO signals from the main
controlloer.
Transfers and fuses the toner image to the
print media.
Moves the last printed sheet out of the printer.
Stops laser scanner operation and high-
voltage biases output.
The printer enters INTR period as the LSTR
period is completed if the main controller
sends another print command.
T-2-1
2-3
2-3

Advertisement

Table of Contents
loading

Table of Contents