NetCol8000-C(070, 130, 190) In-room Chilled Water
Smart Cooling Product
User Manual
Check Item
Fan
Air filter
Differential
pressure
switch
Chilled water
valve
Exhaust valve
Drainage
valve
Pipe
connection
Cable
connections
Issue 09 (2022-12-15)
Expected Result
The fan of the downflow unit is lowered
and secured to the cabinet bottom plate.
The fan has no foreign matter inside.
The air filter is correctly installed
according to the airflow direction marked
on the frame.
The cable ties are securely tightened
around pressure tubes.
There is no foreign matter in pressure
tubes. The pressure tubes show no
obvious bends.
The chilled water valve and its actuator
are securely installed.
The chilled water connector joints have
been wrapped with thermal insulation
foam, and no metal or hose are exposed.
Cables to the chilled water valve and its
actuator are secured. Check that the
manual button on the actuator is reset
(the button bounces up).
The exhaust valve is closed.
The drainage valve is closed.
The water has been filled and air has
been exhausted.
The hose clamps and cable ties of the
condensate water pipe are reliably
secured.
The water inlet and outlet pipes are
properly installed and secured, without
leaks.
The water inlet and outlet pipes are
routed smoothly, without bends.
The drainpipe has a gradient (1:50 is
recommended).
The power voltage is the same as the
rated voltage on the nameplate of the
unit.
Cables are intact.
Copyright © Huawei Digital Power Technologies Co., Ltd.
3 Installation
Actual Result
□Passed □Failed
□Passed □Failed
□Passed □Failed
□Passed □Failed
□Passed □Failed
□Passed □Failed
□Passed □Failed
□Passed □Failed
□Passed □Failed
□Passed □Failed
□Passed □Failed
□Passed □Failed
□Passed □Failed
□Passed □Failed
□Passed □Failed
□Passed □Failed
□Passed □Failed
95