Installation - GE MDP Instruction Manual

Digital time overcurrent relay
Hide thumbs Also See for MDP:
Table of Contents

Advertisement

GEK-100682D
4 INSTALLATION AND MAINTENANCE
4 INSTALLATION AND MAINTENANCE

4.1 INSTALLATION

The relay should be installed in a location that is clean and dry, free from excessive vibration, and well lighted
to facilitate inspection and testing. The relay should be mounted on a vertical surface. An outline and panel
drilling diagram is shown below. External connection schemes on the following pages.
4
Figure 4–1: OUTLINE AND PANEL DRILLING
GE Power Management
MDP Digital Time Overcurrent Relay