Download Print this page

Huawei UPS5000-H Series Quick Manual page 7

100 kva power modules, three-phase three-wire
Hide thumbs Also See for UPS5000-H Series:

Advertisement

UPS5000-H-(1200 kVA-1600 kVA) Quick Guide (100 kVA Power Modules, Three-Phase Three-Wire)
04
Installing Input and Output Cables
Installing Cables (1200 kVA)
Battery
input
05
Verifying the Installation
1. Check that there is no foreign matter in the cabinets.
2. After routing cables and verifying cable connections, seal the gap between cables and the cabinet
using sealing putty. (Remove the paper protective film from the sealing putty and retain the
transparent film. When using the putty, ensure that the transparent film faces upward.)
3. After verifying the installation, reinstall all the covers.
4. Do not remove the dustproof cover before power-on to prevent dust from entering the UPS.
Equipotential
ground point
Signal
cable route
Bypass
Mains
UPS
input
output
input
Paper protective
film
Installing Cables (1600 kVA)
Battery input
Monitoring
Interface Card
Ambient
SmartLi (Master)
T/H Sensor
Dry Contact
Card
NC connection
NO connection
Transparent film
Do not remove the
Sealing putty
dustproof cover before
power-on.
7
Mains input
Bypass input
Battery input
UPS output
Equipotential
ground point
Signal
cable route

Advertisement

loading

This manual is also suitable for:

Ups5000-h-1200k-ntnUps5000-h-1600k-ntn