1MRK 511 403-UEN Rev. K
2.4

Note signs

Bay control REC670
Commissioning manual
Changing the active setting group will inevitably change the IED's operation. Be
careful and check regulations before making the change.
Observe the maximum allowed continuous current for the different current
transformer inputs of the IED. See technical data.
© 2017 - 2021 Hitachi Power Grids. All rights reserved
Section 2
Safety information
M2693-2 v2
IP1497-1 v1
M19-2 v3