C O M M I S S I O N I N G
6.1

Commissioning of an E1 port

6.1.1

Prerequisites

6.1.1.1

CESM1 unit

6.1.1.2

LEDE1 unit

6.1.1.3

PETS

6.1.2

Configuration of an E1 port

24
Before starting the commissioning of a E1 port on the LEDE1 unit, the follow-
ing prerequisites need to be fulfilled:
In a FOX61x, a CESM1 needs to be in operation in slot 11 of the FOX61x
subrack,
In a FOX615, the LEDE1 service unit is inserted into one of the following
slots:
− slot 1 ... 10,
− slot 12 ... 21.
For the installation of the unit, please refer to
lation".
In a FOX612, the LEDE1 service unit is inserted into one of the following
slots:
− slot 7 ... 10,
− slot 12 ... 14.
For the installation of the unit, refer to
A valid ESW is installed on the LEDE1 unit. For the management of ESW,
refer to
"1KHW002466 FOXCST
ESW versions, refer to
"1KHW002459 FOX61x Release
FOXCST needs to be installed on a PC, and a management connection from
the FOXCST to the FOX61x needs to be up and running. For details about
the installation and operation of the FOXCST, please refer to
FOXCST
Operation".
The amount and accessibility of operations depend on the user profile with
which you are logged in. For more information, please refer to
"1KHW002466 FOXCST
Operation".
The PETS on the FOX61x network element must be configured to an appro-
priate synchronization clock source, i.e. a clock source traceable to a PRC.
For the PETS configuration refer to
For the configuration of the E1 port, the following steps have to be per-
formed.
"1KHW002461 FOX615 Instal-
"1KHW002462 FOX612
Operation". For details about compatible
Notes".
"1KHW002467 FOX61x TDM
Installation".
"1KHW002466
Services".
FOX61x
LEDE1