4
PRECAUTIONS FOR USE OF SAFETY
PROGRAMMABLE CONTROLLER
4.3

Precautions for Startup

When new safety-related system will be started up or existing safety-related system will be
changed, confirm the below points.
(1) Confirmation of network connection configuration
(2) Confirmation before writing parameters and program
(3) Usage of a checklist
4
4.3 Precautions for Startup
- 18
Confirm that the CC-Link Safety remote I/O module used is set as designed.
The confirmation items are shown below.
1) Link ID
2) Station No.
3) Transmission speed
For the switch settings of the safety remote I/O station on CC-Link Safety, refer to the
following.
CC-Link Safety System Remote I/O Module User's Manual
Confirm the parameters and program to be written are as designed before writing
them to a programmable controller.
For parameter settings using GX Developer, refer to the following.
GX Developer Version 8 Operating Manual (Safety Programmable Controller)
For definitions and setting ranges of parameter settings using GX Developer, refer to
the following.
CC-Link Safety System Master Module User's Manual
MELSEC-QS CC-Link IE Field Network Master/Local Module User's Manual
Before operation, check if the safety-related system is correctly configured with the
checklist in Appendix 3.