ABB ACS580MV Hardware Manual page 47

Synchronized bypass unit
Hide thumbs Also See for ACS580MV:
Table of Contents

Advertisement

Motor
1.
Motor installed, aligned and alignment protocol available
2.
Motor decoupled from driven load
3.
Ground connection completed
4.
Customer side motor protection set and ready (e.g. winding temperature, vibration)
5.
Motor auxiliaries (e.g. bearing lubrication, heater cooling) ready
Insulation tests
1.
All power cables to drive, and from drive to motor are meggered, and measured values are
within the required limits.
2.
Test report of the megger test available
Note: If the test is carried out by the commissioning engineer of the drive, an additional day per
drive motor combination needs to be reserved. After the test, the feeder cables can be
connected, except at the drive end. The test must comply with the specification.
3.
Optional insulation tests of the drive are completed and documented. Insulation tests of the
drive recommended in case: long storage time (>4 months), humid environment or visible
damages due to transportation/installation.
Power supply
1.
Medium voltage available for start-up of drive
2.
Low voltage auxiliary power available for start-up of drive
Miscellaneous
1.
Sufficient number and correct type of spare parts available
2.
Cooling of drive room ready for load run of drive
3.
Optional equipment ready
Installation checklist 47

Advertisement

Table of Contents
loading

Table of Contents