Connecting the Tubing and Air Supply

This section describes the process for connecting the tubing and air supply to a single acting
PST controller.
Pneumatic Connections
The SVI II ESD is intended for use with industrial compressed air or natural gas systems only
that meet the requirements of ISA standard 7.3. Supply pressure must not exceed 120 psi. A
coalescing filter can be used to assure that the supply air is sufficiently free of oil, water, and
particulate contaminants. Ensure that an adequate pressure relief provision is installed when
the application of system supply pressure could cause peripheral equipment to malfunction.
Installation must be in accordance with local and national compressed air and
instrumentation codes. Table 7 provides the pneumatic connections and air supply
requirements for the SVI II ESD.
Table 7 Pneumatic Connections/Air Supply Requirements
Recommended Piping
Inlet/Outlet
Instrument Air Pressure 30 - 120 psi (2.07 - 8.27 bar) (207 - 827 kPa)
Dew Point
Particulate Matter
Oil Content
Contaminants
© 2016 General Electric Company. All rights reserved.
It is advisable to tube and apply the air supply to the SVI II ESD
NOTE
before connecting the electrical input signal to power it up.
For small actuators it may be necessary to use 1/8" tubing for
NOTE
Autotune to work properly.
1/2" stainless steel or PVC tubing. The length of tubing between
the SVI II ESD and the valve shall be kept as short as possible
and free of kinks
At least 18° F (-8° C) below minimum anticipated ambient tem-
perature
Filtered to 5 microns
Less than 1 ppm w/w