14.1

Operation Types

The operation types are summarized below.
Operation
Startup
Switch power Supply
Stop
Complete Shutdown
Float / equalize Charge
protection Charge
epo (emergency power off) Opens up UPS input and output circuit breakers. Now power flows
14.2

Pre-operational Check

before operating the UpS:
1. make sure all covers/panels are in place and secured.
2. Make sure the temperature in the UPS/Battery room is within specified limits.
3. before starting the UpS, check the power source to make sure AC input power is on.
4. make sure battery breaker's auxiliary A-contact is connected to the terminal block Tb1.
G8000 Series with Isolated output Installation and operation manual
TABLE 11.1 OPERATION TYPES
Description
Starting up and operating the UpS.
Switching power supply source between UpS and bypass.
Stop the inverter and chopper/charger.
Turn off the control power supply. Shut down the UpS completely.
Changing the battery recharge mode between float charge and
equalize charge.
Automatic recharge mode transition from protection charge to float
charge.
through the unit.
CAUTION
Perform the pre-operational check before operating the UPS.