Turn the ON/OFF button on the machine ON.
7.
As the pump starts to build pressure, begin to adjust the valves in the following
manner: start by slowly closing the concentrate valves while slowly opening the
recycle valve (Figure 2.1, Flow Control Center).
CAUTION:
8.
After 20 - 30 minutes of flushing permeate to the drain, ensure all chemical
residue has been removed before hooking up to point of use.
While operating, the pressure range should never operate outside of the pressure
ranges displayed in Table 2.3 (E2/EZ2-Series Primary Pressure Range).
*
Primary pressure temperature for normal operation is 77°F (25°C).
CAUTION:
NOTE: Optimum recovery will vary according to feed water quality.
The concentrate valve is drilled, and when completely closed the machine is run-
ning at the correct concentrate flow for a 75% recovery (Table 2.4, Flow
Specifications for E2/EZ2-Series Machines).
If the temperature of the inlet feed water is not 77°F (25°C) use the Temperature
Correction Factor Table (Technote 113). The proper adjustment of the recycle and
concentrate valves are critical to the correct operation of the machine.
Monitor machine to ensure inlet pressure of 30 - 60 psi
(2.1 - 4.1 bar) is maintained during operation.
Table 2.3
E2/EZ2-Series
Primary Pressure Range*
E2/EZ2-Series
Operating
220 psi
Pressure
(15.2 bar)
Operating
165 - 250 psi
Range
(114. - 17.2 bar)
The E2/EZ2-Series must not operate outside the ranges listed