Panel Installation
Step1 Prepare and install ceiling
Drill 430 mm x 1300 mm( 16.93''x51.18'' )
●
hole into the ceiling based on the layout of
the installation board.
The centre of the ceiling opening should
match the centre of the body of the indoor
unit.
NOTICE
In order to keep the ceiling level and prevent
vibrations, reinforce the strength of the ceiling
when necessary.
Once the ceiling is cut, remove the installation
●
board.
then install the ceiling.
●
Step 2 Panel Installation
Model A
NOTICE
The air grille received by the customer is not
●
tightened by the wire rope,but is specially
designed to be loose for easy installation.
Grab air grille with your ngers and pull it out
●
slowly in the direction of the arrow.
Grab at these locations
Pull the panel grille out of the panel, x the
●
cassette panel to the one-way cassett by two
plastic buckles.
Manually rotate the air de ector, x the panel
●
to the cassette by using 3×M4*22 screws and a
ST3.9*16 screw.
M4*22 screw
NOTICE
Eight M4*22 screws are
supplied, two of which are
spare. Two ST3.9*16 screws
are supplied, one of which is spare.
Before xing this screw, you need to open the screw cover;
and after xing screw, please close the cover.
Open the two covers on both sides of the panel ,
●
x the panel to the cassette by using 3× M4*22
screws.
M4*22 screw
Connect the display board to the main control
●
board, up to four wires are required to connect.
NOTICE
NOTICE
The corresponding colors or corresponding
pins are connected each other.
(white 10-core)
(red 5-core)
when connection is completed, please clip
the wires to the buckle.
ST3.9*16 screw
(white 5-core)
( 4 core)
Page 43