Assembly Procedure PC4000
3.6.
Mounting of Hydraulic Oil Cooler (Z21866)
1.
Lift the Hydraulic Oil Cooler.
Lifting eyes are delivered with the machine.
2.
Align the Hydraulic Oil Cooler with the superstructure.
(Pay attention to the course of the hydraulic lines!)
3.
Lower the Hydraulic Oil Cooler fully down and install all 8 bolts .
Tighten the bolts with the resp. torque.
(Refer to section 4.12 of the Maintenance Manual).
4.
Connect all hoses, pipes and electric cables.
PC4000Asrev05
Edition 08/2005