Section 11
Testing functionality by secondary injection
11.5.4.1
Function revision history
Document
revision
A
B
C
D
E
F
J
K
11.5.4.2
Check of undervoltage levels
This test is relevant if the setting BlkDiffAtULow = Yes.
Check of U1Low
Procedure
1.
Connect voltages to the IED according to valid connection diagram and figure 27.
2.
Apply voltage higher than the highest set value of UDTrip, U1Low and U2Low to the U1 three-
phase inputs and to one phase of the U2 inputs according to figure 27.
The voltage differential START signal is set.
124
Product
History
revision
2.2.1
-
2.2.1
-
2.2.2
-
2.2.3
-
2.2.3
-
2.2.4
-
2.2.4
-
2.2.5
-
© 2017 - 2022 Hitachi Energy. All rights reserved
1MRK 511 403-UEN Rev. L
GUID-04679E4E-E0D2-4BA6-A002-4020E52DB973 v1
SEMOD175258-71 v2
SEMOD175258-75 v3
Bay control REC670
Commissioning manual