10
Building Technologies
Fire Safety & Security Products
Testing the product operability
Prevent the remote transmission from triggering for no reason.
When testing building installations or controlling devices from external
companies, you must work with the responsible people.
The activation of fire control installations for test purposes must not cause
injury or damage to the building installations. The following instructions must be
observed:
‒ Use the correct potential for activation; this is generally the potential of the
building installation.
‒ Only check controls up to the interface (relay with blocking option).
‒ Make sure that only the controls to be tested are activated.
Inform people before testing alarming equipment and allow for any potential
panic responses.
Inform people of any noise or mist that may be produced.
Inform the relevant points that will receive alarms and faults before testing
remote transmission.
Changes to the system layout and products
Modifications to the system and to individual products may lead to faults,
malfunctioning and safety risks. The written consent of Siemens and the relevant
safety bodies must be obtained for modifications or additions.
Modules and spare parts
Components and spare parts must comply with the technical specifications
defined by Siemens. Only use products which have been specified or
recommended by Siemens.
Only use fuses with the specified fuse characteristics.
Wrong battery types and improper battery changing lead to a risk of explosion.
Only use the specified battery type or an equivalent battery type recommended
by Siemens.
Batteries must be disposed of in an environmentally friendly manner. Observe
national guidelines and specifications.