Installation and setting
Capacitor formation (if necessary)
•
Remove the system upper cover
•
Switch "1" of S1 on D1 to "ON".
w
•
Select test programs by pressing "kV+" button until "P06" is displayed.
•
Press lamp button to start the capacitor formation.
w
w
Approximately every 6 minute the voltage values is increased. The charging sequence is
increased as follows:
w
At the 353 V level the charging will continue for another 48 minutes to decrease and stabi-
lize the capacitors internal leakage current.
w
Duration: Approximately 100 minutes.
•
Switch "1" of S1 on D1 to "OFF"
Siemens-Elema AB
Solna, Sweden
This will display the program version:
kVmAs
vErX.X = Version X.X (depends on software version installed).
The test program starts with displaying:
kVmAs
CAPFor = Capacitor formation program
After a short while, starts the program to display the actual voltage in the
capacitor bank:
kVmAs
CAP150 = 150 Volt.
150 - 250 - 299 - 325 - 337 - 345 - 348 - 351 - 353
If the formation is successfully finished the display will show:
kVmAs
P06 PASS = Capacitor formation completed.
SPR8-220.033.03
Rev. 02
10.02
Page 5 of 12
MOBILETT Plus HP
SPS-UD
2 - 5